Construction Update: 4-14-14

Week of April 6th

Project Activities:

Impact:

PE Complex
  • Installation of roof
  • Metal framing installation
  • Rough-in for mechanical and plumbing
  • Backfilling (See Impact note)

 

  • Contractor will cone- off 8 parking spaces in parking lot J to allow dump trucks to back up onto construction site. See below:

Area to be coned off. PE Complex Construction Site

New Science Building
  • Continue sewer connection and storm drain pipe rerouting - north of CHS building and LADM's north lawn area
  • Footing layout, excavation and rebar for Lab building
  • Concrete pour on 4-9-2014 (6 trucks)

 

  • Parking lot F and ADA access ramp are closed
  • Extend yellow fence west of OE-1 planter
  • Construction noise from on-site activity
  • CHS north pedestrian walkway access is closed. Pedestrians are directed to detour.
  • CHS north-east staircase will be closed.
  • Delivery trucks/ increased traffic. Proper traffic control will be provided.
OE2 Building
  • Underground utility installation
  • East wing retaining wall rebar installation and forming
  • West wing footing excavation, rebar & forming installation

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
LRC Temporary Parking lot
  • Grading
  • Retaining wall installation
  • Concrete pour for ADA parking stalls

 

  • Increased construction traffic on fire access road by LRC
  • Construction noise from on-site activity
  • Parking spaces around LRC generator are planned to be closed to ensure safety during construction. Temporary drop-off and pick-up parking will be accommodated.
  • Access to IT Department will be limited and closed at time. Communication with IT Department will be maintained throughout operation.
  • Delivery trucks / increased traffic with dirt off-haul and concrete pour. Proper traffic control will be provided.

Week of April 13th

Project Activities:

Impact:

PE Complex
  • Installation of roof
  • Drywall installation
  • Rough-in for mechanical and plumbing
  • Irrigation installation

 

  • Delivery trucks/ increased traffic
  • No major impact activities
New Science Building
  • Restore the LADM's north lawn area
  • Storm drain system installation at the south site / canyon
  • Footing layout, excavation and rebar for Lab building
  • Concrete pour on 4-16-2014 (6 trucks)
  • Relocate the underground irrigation pipe

 

  • Parking lot F and ADA access ramp are closed
  • Extend yellow fence west of OE-1 planter
  • Construction noise from on-site activity
  • CHS north pedestrian walkway access and CHS north-east staircase are closed. Directional and informational signage are provided for public safety
  • Delivery trucks/ increased traffic. Proper traffic control will be provided.
OE2 Building
  • Underground utility installation
  • East wing retaining wall rebar installation and forming
  • West wing footing rebar & forming installation

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
LRC Temporary Parking lot
  • Grading
  • Retaining wall installation

 

  • Increased construction traffic on fire access road by LRC
  • Construction noise from on-site activity
  • Parking spaces around LRC generator are planned to be closed to ensure safety during construction. Temporary drop-off and pick-up parking will be accommodated.
  • Access to IT Department will be limited and closed at time. Communication with IT Department will be maintained throughout operation.

Week of April 20th

Project Activities:

Impact:

PE Complex
  • Installation of roof
  • Drywall installation
  • Rough-in for mechanical and plumbing
  • Irrigation installation
  • Concrete & asphalt paving in Parking lot J
  • Paving at intersection of Campus Drive and Service Road

 

  • Equipment in use at parking lot J
  • Campus drive will remain open, Service road will be closed for one day.
New Science Building
  • Storm drain system installation
  • Footing layout, excavation and rebar for Lab building
  • Concrete pour on 4-23-2014 (6-8 trucks)
  • Concrete pour on 4-25-2014 (6-8 trucks)
  • Irrigation transite abatement

 

  • Parking lot F and ADA access ramp are closed
  • Extend yellow fence west of OE-1 planter
  • Construction noise from on-site activity
  • CHS north pedestrian walkway access and CHS north-east staircase are temporarily closed. Directional and informational signage are provided for public safety
  • Delivery trucks/ increased traffic. Proper traffic control will be provided.
OE2 Building
  • Underground utility installation
  • East wing retaining wall rebar installation and forming
  • West wing footing rebar and forming installation

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
LRC Temporary Parking lot
  • Grading
  • Retaining wall installation
  • Asphalt base installation
  • Electrical work

 

  • Increased construction traffic on fire access road by LRC
  • Construction noise from on-site activity
  • Parking spaces around LRC generator are planned to be closed to ensure safety during construction. Temporary drop-off and pick-up parking will be accommodated
  • Access to IT Department will be limited and closed at time. Communication with IT Department will be maintained throughout operation.