We will make every effort to assure the accuracy and completeness of these updates; however, there will be some changes and adjustments as construction progresses.

How Will Construction Activity Affect You?

  • Construction personnel and equipment will be on campus drive periodically throughout construction. Please proceed with caution. 
  • With construction activity on-going safety is always a major priority for both staff and students. With this in mind we wanted to again ensure that both staff and students remain outside of the construction activity areas that have been established. These areas are clearly donated with temporary fencing. If access is needed within any construction areas proper notification, escort and safety measures (hard hats, vests, etc.) are required. 
  • Campus Drive open. 
    Parking lots open: CDC, A1, A, B, C, D, E (west ¾), F, G, gym lot H, I, Aquatic Center, and overflow. 
  • Parking lots closed: East ¼ of parking lot E. 
  • East entrance right turn lane exiting Campus Drive will be closed from time to time during work hours due to work for electronic marque. Please proceed with caution. 
  • Work will be on-going in and around the M&O yard. Please proceed with caution. 
  • Work will be on-going in and around the CDC drop-off & pick-up area. Please proceed with caution. 
  • Sunday, December 18th, the M&O road will be shut down for slurrying. It will be able to open back up first thing Monday morning, December 19th.

Week of December 19th

Parking, ADA Access & Lighting Improvements (PAL)

Campus wide

  • Trenching, forming and pouring of light pole bases and electrical wiring
  • Lighting controls start-up, testing & commissioning
  • Miscellaneous sign installation

M&O Access Road and Yard

  • Repair of exterior M&O yard fencing
  • Electrical equipment enclosure preparation
  • Trenching for electrical conduit

Lot A – Parking Lot A

  • Punch list work

Lot B – Parking Lot B

  • Punch list work

Lot C – Parking Lot C

  • Punch list work

Lot D – Parking Lot D

  • Punch list work

Lot E – Parking Lot E

  • Forming and pouring for ADA pathway/walkway
  • Forming and pouring for wall & stair footings

Lot F – Parking Lot F

  • Punch list work

Lot G – Parking Lot G

  • Punch list work

Lot H – Parking lot H

  • Punch list work

Lot I – Parking lot I

  • Punch list work

Gym Parking lot

  • Punch list work

Campus Drive

  • East entrance electronic marque work

Math and Science Annex (MSA)

  • Math Modular buildings: no work scheduled
  • Science Modular buildings: steam generator & autoclave installation

Old Library Demolition

Data Relocation

  • No work scheduled

Library Demolition

  • Punch list work
  • Staining of concrete panels

CRF LEED Landscaping

  • No work scheduled

Learning Resource Center

  • No work scheduled

Week of December 26th

Parking, ADA Access & Lighting Improvements (PAL)

Campus wide

  • Trenching, forming and pouring of light pole bases and electrical wiring
  • Lighting controls start-up, testing & commissioning
  • Miscellaneous sign installation

M&O Access Road and Yard

  • Repair of exterior M&O yard fencing
  • Electrical equipment enclosure preparation
  • Trenching for electrical conduit
  • Striping for M&O road

Lot A – Parking Lot A

  • Punch list work

Lot B – Parking Lot B

  • Punch list work

Lot C – Parking Lot C

  • Punch list work

Lot D – Parking Lot D

  • Punch list work

Lot E – Parking Lot E

  • Forming and pouring for ADA pathway/walkway
  • Forming and pouring for wall & stair footings

Lot F – Parking Lot F

  • Punch list work

Lot G – Parking Lot G

  • Punch list work

Lot H – Parking lot H

  • Punch list work

Lot I – Parking lot I

  • Punch list work

Gym Parking lot

  • Punch list work

Campus Drive

  • West entrance marque installation
  • East entrance electronic marque work

Math and Science Annex (MSA)

  • Math Modular buildings: no work scheduled
  • Science Modular buildings: steam generator & autoclave installation

Old Library Demolition

Data Relocation

  • No work scheduled

Library Demolition

  • Punch list work
  • Staining of concrete panels

CRF LEED Landscaping

  • No work scheduled

Learning Resource Center

  • No work scheduled