Construction Update: 12-15-13

Week of December 15th

Project Activities: Impact:

PE Complex

  • Prepare for Pool Area work
  • Selective demolition in pool area/ Concrete cutting
  • Delivery trucks/ increased traffic
  • No access to soccer field
  • Loss of 7 parking spaces at Lot J
  • Construction  noise at Aquatics Center

Week of December 22th

Project Activities: Impact:

PE Complex

  • Pool Area work
  • Installation of footings for fence posts
  • Shut off water to east side of Campus for water tie –in
  • Delivery trucks/ increased traffic
  • Partial closure of Campus Drive
  • No access to soccer field
  • Loss of 7 parking spaces at Lot J
  • Construction  noise at Aquatics Center

Parking Lot D & E

  • Striping parking lot D & E
  • Parking lot E will be closed Dec. 23 & 24.
  • Parking lot D visitor stalls will be closed Dec. 23 & 24.

Circuit C Project

  • Shutdown Circuit C for 2-4 hours 
  • No power at CHS and east wing of LADM’s labs during the holiday break.

New Science Building

  • Construction starts
  • Parking lot F and ADA ramp will be closed for construction until July 2015.
  • Construction site fence installation.

OE2 Building

  • Pre-Construction activities
  • Contractor Mobilization
  • Temporary non-accessible pedestrian walkway from Lot I to Lot H.
  • Bookstore deliveries will be coordinated with M&O.

Week of December 29th

Project Activities: Impact:

PE Complex

  • Pool Area Work
  • Connection to Sewer line at Campus Drive. Campus Drive will be partially closed for two days.
  • Delivery trucks/ increased traffic
  • Partial closure of Campus Drive
  • No access to soccer field
  • Loss of 7 parking spaces at Lot J
  • Construction  noise at Aquatics Center

Parking Lot D & E

  • Striping parking lot D & E
  • Parking lot E will be closed Dec. 23 & 24.
  • Parking lot D visitor stalls will be closed Dec. 23 & 24.

New Science Building

  • Contractor mobilization
  • Parking lot F and ADA ramp will be closed for construction until July 2015. 
  • Construction fence installation

OE2 Building

  • Pre-Construction activities
  • Contractor Mobilization
  • Temporary non-accessible pedestrian walkway from Lot I to Lot H.
  • Bookstore deliveries will be coordinated with M&O.