Construction Update: 11-12-13

Week November 3rd

Project Activities

Impact

PE Complex

  • Concrete reinforcement
  • Storm Drain Pipes
  • Excavation for water retention system

 

  • Heavy Equipment in use at soccer field.
  • Construction noise at Aquatics Center.
  • No access to soccer field.
  • Increased traffic on access road between soccer field and tennis courts.
  • Loss of 7 parking spaces at Lot J.

Week of November 10th

Project Activities

Impact

PE Complex

  • Foundations
  • Concrete reinforcement
  • Concrete formwork
  • Installation of water retention system
  • Heavy Equipment in use at soccer field.
  • Construction noise at Aquatics Center.
  • No access to soccer field.
  • Increased traffic on access road between soccer field and tennis courts.
  • Loss of 7 parking spaces at Lot J.

Week of November 17th

Project Activities

Impact

PE Complex

  • Foundations
  • Installation of water retention system
  • Heavy Equipment in use at soccer field.
  • Construction noise at Aquatics Center.
  • No access to soccer field.
  • Increased traffic on access road between soccer field and tennis courts.
  • Loss of 7 parking spaces at Lot J.