We will make every effort to assure the accuracy and completeness of these updates; however, there will be some changes and adjustments as construction progresses.

HOW WILL CONSTRUCTION ACTIVITY AFFECT YOU?

  • Construction personnel and equipment will be on campus drive periodically throughout construction. Please proceed with caution.
  • With construction activity on-going safety is always a major priority for both staff and students. With this in mind we wanted to again ensure that both staff and students remain outside of the construction activity areas that have been established. These areas are clearly donated with temporary fencing. If access is needed within any construction areas proper notification, escort and safety measures (hard hats, vests, etc.) are required. 
  • Campus Drive is open. 
  • Parking lots open: CDC, A1, A, B, C, D, F, G, H, I, overflow, and the Aquatic Center. 
  • Parking lots closed: E and gym lot. 
  • OE-1 stairs and landing will be poured Tuesday 10/18/11. OE-1 Landing will be open as soon as possible after pour…Thursday at the latest. During this construction operation the north entrance/exit to the OE-1 building will be closed. It will remain available in case of emergency. Please use alternate entrances/exits to the OE-1 building during this time. Signage will be in-place to aid in notification and way finding. 
  • Temporary fencing around old library demolition project site is in-place. West-half of the main quad and pathways/walkways directly north and south of the old library will be closed. 
  • Heavy demolition at the old library is on-going. Noise and vibration will be heard throughout campus. Full safety measures will be exercised during this operation to ensure the safety of the staff and students. 
  • Demolition debris haul off is on-going. Construction trucks will be utilizing Campus Drive throughout this operation for haul off routes. Please proceed with caution. 
  • Transporting of soil for backfill of old library demolition basement will be beginning. Soil is being taken from area west of the soccer field. Construction trucks will be utilizing Campus Drive throughout this operation. Please use caution. Full safety measures will be exercised during this operation to ensure the safety to the staff and students. 
  • Parking spaces will be impacted up at the Aquatic Center parking lot periodically with the on-going CRF landscaping project. Areas will be sectioned off and kept to a minimum.

Week of October 17th

Parking, ADA Access & Lighting Improvements (PAL)

Campus wide
  • Trenching, forming and pouring of light pole bases and electrical wiring
  • Hydroseeding on slope associated with M&O sewer line
Lot A – Parking Lot A
  • Punch list work
Lot B – Parking Lot B
  • Punch list work
Lot C – Parking Lot C
  • Punch list work
Lot D – Parking Lot D
  • No work scheduled
Lot E – Parking Lot E
  • Forming & pouring islands and diamonds within parking lot
  • Forming & pouring for ADA pathway/walkway
Lot F – Parking Lot F
  • Punch list work
Lot G – Parking Lot G
  • Punch list work 
  • OE-1 Stairs: pour & strip form on stairs and landing
Lot H – Parking lot H
  • Punch list work
Lot I – Parking lot I
  • Punch list work
Gym Parking lot
  • Pathway/flatwork grading, forming and pouring
  • Landscape installation
Campus Drive
  • No work scheduled

Math and Science Annex (MSA)

  • Math Modular buildings: no work scheduled
  • Science Modular buildings: no work scheduled

Old Library Demolition

Data Relocation
  • No work scheduled
Library Demolition
  • Heavy demolition in the basement area
  • Hauling off demolition debris
  • Begin backfill of basement area

CRF LEED Landscaping

  • Decomposed granite installation
  • Planting 
  • Cobble installation
  • Concrete pour for bike rack pad and mow curb

Week of October 24th

Parking, ADA Access & Lighting Improvements (PAL)

Campus wide
  • Trenching, forming and pouring of light pole bases and electrical wiring
Lot A – Parking Lot A
  • Punch list work
Lot B – Parking Lot B
  • Punch list work
Lot C – Parking Lot C
  • Punch list work
Lot D – Parking Lot D
  • No work scheduled
Lot E – Parking Lot E
  • Forming and pouring for ADA pathway/walkway 
  • Excavation for stair footings
Lot F – Parking Lot F
  • Punch list work
Lot G – Parking Lot G
  • Punch list work
  • OE-1 Stairs: handrail installation
Lot H – Parking lot H
  • Punch list work
Lot I – Parking lot I
  • Punch list work
Gym Parking lot
  • Handrail installation
  • Landscape installation
Campus Drive
  • No work scheduled

Math and Science Annex (MSA)

  • Math Modular buildings: no work scheduled
  • Science Modular buildings: no work scheduled

Old Library Demolition

Data Relocation
  • No work scheduled
Library Demolition
  • Backfill of basement area

CRF LEED Landscaping

  • Planting 
  • Cobble installation