How Will Construction Activity Affect You?

  • Construction personnel and equipment will be on campus drive periodically throughout construction. Please proceed with caution. 
  • With construction activity on-going safety is always a major priority for both staff and students. With this in mind we wanted to again ensure that both staff and students remain outside of the construction activity areas that have been established. These areas are clearly donated with temporary fencing. If access is needed within any construction areas proper notification, escort and safety measures (hard hats, vests, etc.) are required. 
  • Campus Drive is open.
  • Parking lots open: CDC, A1, A, B, C, D, F, G, H, I, and the Aquatic Center. 
  • Parking lots closed: E, gym lot and overflow. 
  • Temporary fencing around old library demolition project site is in-place. West-half of the main quad and pathway’s/walkway’s directly north and south of the old library will be closed. 
  • Heavy demolition at the old library is on-going. Noise and vibration will be heard throughout campus. Full safety measures will be exercised during this operation to ensure the safety of the staff and students.
  • Demolition debris haul off is on-going. Construction trucks will be utilizing Campus Drive throughout this operation for haul off routes. Please proceed with caution. 
  • Parking spaces will be impacted up at the Aquatic Center parking lot periodically with the on-going CRF landscaping project. Areas will be sectioned off and kept to a minimum.

Week of October 3rd

Parking, ADA Access & Lighting Improvements (PAL)

Campus wide

  • Trenching, forming and pouring of light pole bases and electrical wiring 
  • Sewer line installation up to M&O yard

Lot A – Parking Lot A

  • Punch list work

Lot B – Parking Lot B

  • Punch list work

Lot C – Parking Lot C

  • Punch list work

Lot D – Parking Lot D

  • No work scheduled

Lot E – Parking Lot E

  • Subgrade preparation
  • Forming & pouring for curb and gutter

Lot F – Parking Lot F

  • Punch list work

Lot G – Parking Lot G

  • Punch list work

Lot H – Parking lot H

  • Punch list work

Lot I – Parking lot I 

  • Punch list work

Gym Parking lot 

  • Pathway/flatwork grading, forming and pouring 
  • Landscape installation

Campus Drive

  • No work scheduled

Math and Science Annex (MSA)

  • Math Modular buildings: no work scheduled 
  • Science Modular buildings: finalizing punch list work

Old Library Demolition

Data Relocation

  • No work scheduled

Library Demolition 

  • Hauling off demolition debris

CRF LEED Landscaping

  • Weed abatement 
  • Tree installation 
  • Concrete paver installation 
  • Decomposed granite installation

Week of October 6th

Parking, ADA Access & Lighting Improvements (PAL)

Campus wide

  • Trenching, forming and pouring of light pole bases and electrical wiring

Lot A – Parking Lot A

  • Punch list work

Lot B – Parking Lot B

  • Punch list work

Lot C – Parking Lot C 

  • Punch list work

Lot D – Parking Lot D

  • No work scheduled

Lot E – Parking Lot E

  • Subgrade preparation
  • Forming for ADA pathway/walkway

Lot F – Parking Lot F

  • Punch list work

Lot G – Parking Lot G

  • Punch list work

Lot H – Parking lot H

  • Punch list work

Lot I – Parking lot I 

  • Punch list work

Gym Parking lot 

  • Pathway/flatwork grading, forming and pouring 
  • Landscape installation

Campus Drive

  • No work scheduled

Math and Science Annex (MSA)

  • Math Modular buildings: no work scheduled 
  • Science Modular buildings: no work scheduled

Old Library Demolition

Data Relocation

  • No work scheduled

Library Demolition 

  • Hauling off demolition debris

CRF LEED Landscaping 

  • Concrete paver installation 
  • Decomposed granite installation 
  • Soil preparation