Construction Update: 9-27-13

Week of September 29th

Project Activities: Impact:

OE2 Demo

  • Underground electrical and electrical shutdowns / switchovers
  • Final building and site demolition
  • Final site utility demolition
  • Temporary non-accessible pedestrian walkway from Lot I to Lot H.
  • Bookstore deliveries will be coordinated with M&O.
  • On-going noise will be kept to a minimum.
  • Multiple electrical shutdowns / switchovers will take place this week and effect OE1 Building and buildings on Circuit B (MSA, Solar Farm, Sat/TV Com Tower/Water Tank, Gym and LADM). Shutdowns / switchovers will be short in duration and majority will be done off-hours to ensure no interruption to campus operations. Please turn off all electronics prior to leaving for the day.

PE Complex

  • Excavation & begin utilities rough in
  • Tree relocation
  • Underground utilities

 

  • Heavy Equipment in use at soccer field
  • Construction  noise at Aquatics Center

 

Week of October 6th

Project Activities:

Impact:

OE2 Demo

  • Final building and site demolition
  • Final site utility demolition
  • Final rough grading
  • Site cleanup

 

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H.
  • Bookstore deliveries will be coordinated with M&O.
  • On-going noise will be kept to a minimum.

 

PE Complex

  • Grading
  • Excavation
  • Underground utilities
  • Increased traffic on access road between soccer field and tennis courts
  • No access to soccer field
  • Loss of 7 parking spaces at Lot J

Week of October 12th

Project Activities:

Impact:

OE2 Demo

  • Punch list

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H.
  • Bookstore deliveries will be coordinated with M&O.
  • On-going noise will be kept to a minimum.

 

PE Complex

  • Building pad prep and certification
  • Underground utilities

 

 

 

  • No access to soccer field
  • Loss of 7 parking spaces at Lot J