Construction Update 8/23/2013

Week of August 26th

Project Activities

Impact

OE2 Demo

  • Site utility cut / cap demolition
  • Underground electrical

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H.
  • Bookstore deliveries will be coordinated with M&O.
  • On-going noise will be kept to a minimum.
  • New speed bumps on Campus Drive will take some getting used to…drive slowly.
  • Electrical shutdown of Circuit B is scheduled for Wednesday, 8/28 at 5:00 AM. Shutdown will be short in duration and therefore no temporary power will be required. Power will be restored prior to staff and students arrival on-campus.

Week of September 1st

Project Activities

Impact

OE2 Demo

  • Site utility cut / cap demolition
  • Underground electrical

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H.
  • Bookstore deliveries will be coordinated with M&O.
  • On-going noise will be kept to a minimum.
  • New speed bumps on Campus Drive will take some getting used to…drive slowly.

Week of September 8th

Project Activities

Impact

OE2 Demo

  • Underground electrical

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H.
  • Bookstore deliveries will be coordinated with M&O.
  • On-going noise will be kept to a minimum.
  • New speed bumps on Campus Drive will take some getting used to…drive slowly.

Week of September 8th

Project Activities

Impact

PE Complex

  • Fencing
  • Mobilization
  • Staging
  • Increased traffic on access road between soccer field and tennis courts
  • No access to soccer field
  • Loss of 7 parking spaces at Lot J