Crafton Hills College Construction Update 8/22/11:

We will make every effort to assure the accuracy and completeness of these updates; however, there will be some changes and adjustments as construction progresses.

HOW WILL CONSTRUCTION ACTIVITY AFFECT YOU? 

  • Construction personnel and equipment will be on campus drive periodically throughout construction. Please proceed with caution. 
  • With construction activity on-going safety is always a major priority for both staff and students. With this in mind we wanted to again ensure that both staff and students remain outside of the construction activity areas that have been established. These areas are clearly donated with temporary fencing. If access is needed within any construction areas proper notification, escort and safety measures (hard hats, vests, etc.) are required. 
  • Campus Drive is open. 
  • Parking lots open: CDC, A1, A, B, C, D, F, G, H, I, and the Aquatic Center. 
  • Parking lots closed: E and overflow. 
  • The pathway/flatwork from the Science complex and OE complex will not be open 8/22/11. The goal is to have it available for use mid-to-late next week. The temporary pathway/walkway for pedestrian access to and from the Science complex and OE complex will be via the temporary pathway/walkway used throughout the first week of school. 
  • Access to soccer field is routed via the walkway south and west of the tennis courts. This route will continue for the duration of the MSA project. 
  • Temporary fencing around old library demolition project site is in-place. West-half of the main quad and pathway’s/walkway’s directly north and south of the old library will be closed. 
  • Heavy demolition at the old library is scheduled to begin 8/22/11. Noise and vibration will be heard throughout campus. Full safety measures will be exercised during this operation to ensure the safety of the staff and students. Math & Science Annex bathrooms will be shut down for water chlorination all day Monday 8/22/11. 
  • Parking spaces will be impacted up at the Aquatic Center parking lot periodically with the on-going CRF landscaping project. Areas will be sectioned off and kept to a minimum.

Week of August 22nd

Parking, ADA Access & Lighting Improvements (PAL

Campus wide 

 

  • Trenching, forming and pouring of light pole bases and electrical wiring
Lot A – Parking Lot A

 

  • Punch list work
Lot B – Parking Lot B 
  •  Punch list work
Lot C – Parking Lot C

  • Punch list work 
  • Form & pour flatwork, stairs and ADA accessible ramps 
  • Landscape installation
Lot D – Parking Lot D
  • No work scheduled
Lot E – Parking Lot E
  • Clear & grub 
  • Asphalt pavement demolition
Lot F – Parking Lot F
  • Form & pour flatwork, stairs and ADA accessible ramps 
  • Landscape installation
Lot G – Parking Lot G
  • Grade, form and pour for electrical equipment enclosure 
  • Landscape installation
Lot H – Parking lot H
  • Punch list work
Lot I – Parking lot I 
  • Grading and forming for electrical equipment enclosure 
  • Landscape installation
Gym Parking lot
  • Clear & grub and finalize demolition 
  • Survey layout
Campus Drive
  • No work scheduled

Math and Science Annex (MSA)

  • Landscape installation 
  • On-going exterior site work 
  • Math Modular buildings: punch list work on-going 
  • Science Modular buildings: water chlorination and punch list 
  • FF&E delivery and installation on-going

Old Library Demolition

Data Relocation
  • Punch list and testing of the HVAC system
Library Demolition
  • Heavy demolition scheduled to begin

CRF LEED Landscaping

  • Contractor to begin mobilization of temporary fencing and equipment 
  • Initial clear & grub and demolition activities

Week of August 29th

Parking, ADA Access & Lighting Improvements (PAL)

Campus wide
  • Trenching, forming and pouring of light pole bases and electrical wiring
Lot A – Parking Lot A
  • Punch list work
Lot B – Parking Lot B
  • Punch list work
Lot C – Parking Lot C 

 

  • Punch list work 
  • Form & pour flatwork, stairs and ADA accessible ramps 
  • Landscape installation
Lot D – Parking Lot D
  • No work scheduled
Lot E – Parking Lot E
  • Finalize clear & grub and demolition 
  • Irrigation piping trenching and installation 
  • Electrical conduit trenching and installation
Lot F – Parking Lot F
  • Form & pour flatwork, stairs and ADA accessible ramps 
  • Landscape installation
Lot G – Parking Lot G
  • Grade, form and pour for electrical equipment enclosure 
  • Landscape installation
Lot H – Parking lot H
  • Punch list work
Lot I – Parking lot I 

 

  • Grading and forming for electrical equipment enclosure 
  • Landscape installation
Gym Parking lot
  • Irrigation piping trenching and installation 
  • Electrical conduit trenching and installation 
  • Pathway/flatwork layout and grading
Campus Drive (East-End - from just north of parking lot I to top of east-end of Campus Drive) 
  • Project team is in process of coordinating this work. Work is tentatively scheduled to begin week of August 29th. Confirmation forthcoming.

Math and Science Annex (MSA) 

  • Landscape installation 
  • On-going exterior site work 
  • Math Modular buildings: punch list work on-going 
  • Science Modular buildings: punch list work on-going 
  • FF&E delivery and installation on-going

Old Library Demolition

Data Relocation
  • No work scheduled
Library Demolition 

 

  • Heavy demolition

CRF LEED Landscaping

  • Finalize clear & grub and demolition activities 
  • Concrete paver subgrade preparation and installation 
  • Irrigation installation