Construction Update 8/19/2013

Week of August 19th

Project Activities Impact
OE2 Demo
  • Site utility cut / cap demolition
  • Underground electrical
  • Temporary non-accessible pedestrian walkway from Lot I to Lot H.
  • Bookstore deliveries will be coordinated with M&O.
  • On-going noise will be kept to a minimum.
  • New speed bumps on Campus Drive will take some getting used to…drive slowly.
  • Electrical shutdown of Circuit B is tentatively scheduled for Saturday, 8/24. Affected buildings or systems are as follows: MSA, Solar Farm, Sat/TV Com Tower/Water Tank, OE-1, Bookstore, Bookstore Classrooms, Gym and LADM. Shutdown will be short in duration and all required temporary power necessary will be coordinated prior to shutdown.

OE1 Roofing Project

  • Project Complete

Projected Completion Date: August 18, 2013

  • OE1 building open to normal operations

Week of August 26th

Project Activities

Impact

OE2 Demo
  • Site utility cut / cap demolition
  • Underground electrical
  • Temporary non-accessible pedestrian walkway from Lot I to Lot H.
  • Bookstore deliveries will be coordinated with M&O.
  • On-going noise will be kept to a minimum.
  • Speed bumps on Campus Drive will take some getting used to…drive slowly.
  • Electrical shutdown of Circuit F is tentatively scheduled for one day between 8/26 – 9/7. Affected buildings or systems are as follows: Aquatic Center and Site Lighting. Shutdown will be short in duration and all required temporary power necessary will be coordinated prior to shutdown.

Week of September 1st

Project Activities

Impact

OE2 Demo
  • Underground electrical
  • Temporary non-accessible pedestrian walkway from Lot I to Lot H.
  • Bookstore deliveries will be coordinated with M&O.
  • On-going noise will be kept to a minimum.
  • Speed bumps on Campus Drive will take some getting used to…drive slowly.
  • Electrical shutdown of Circuit F is tentatively scheduled for one day between 8/26 – 9/7. Affected buildings or systems are as follows: Aquatic Center and Site Lighting. Shutdown will be short in duration and all required temporary power necessary will be coordinated prior to shutdown.
  • Electrical shutdown of Circuit B is tentatively scheduled for Saturday, 9/7. Affected buildings or systems are as follows: MSA, Solar Farm, Sat/TV Com Tower/Water Tank, OE-1, Bookstore, Bookstore Classrooms, Gym and LADM. Shutdown will be short in duration and all required temporary power necessary will be coordinated prior to shutdown.