Construction Update 8/1/2013

Week of August 5th

Project Activities

Impact

OE2 Move Out and Demo
  • Finalize irrigation controller relocation
  • Site utility cut / cap demolition
  • Site demolition
  • Building heavy demolition
  • Underground electrical
  • Pedestrians are to use the temporary pedestrian walkway from Lot I to Lot H.
  • Bookstore deliveries will be coordinated with M&O.
  • With heavy demolition of the existing OE2 building there will be increased noise around this area. Trucks will also be on Campus Drive hauling demolition debris throughout the day.
  • During demolition of the west edge of the building, the walkway adjacent to the Bookstore Classroom building will be closed for safety.
  • New speed bumps on Campus Drive will take some getting used to…drive slowly.

OE1 Roofing Project

  • 30 day cure period

Projected Completion Date: August 18, 2013

  • OE1 building open to normal operations.

Week of August 12th

Project Activities Impact
OE2 Move Out and Demo
  • Site utility cut / cap demolition
  • Site demolition
  • Building heavy demolition
  • Underground electrical
  • Temporary pedestrian walkway from Lot I to Lot H.
  • Bookstore deliveries will be coordinated with M&O.
  • With heavy demolition of the existing OE2 building there will be increased noise around this area. Trucks will also be on Campus Drive hauling demolition debris throughout the day.
  • During demolition of the west edge of the building, the walkway adjacent to the Bookstore Classroom building will be closed for safety.
  • New speed bumps on Campus Drive will take some getting used to…drive slowly.
OE1 Roofing Project
  • Final roof coating (Sat & Sun)
  • Clean-up
Projected Completion Date: August 18, 2013
  • Building ventilation will be off Sat & Sun during final coating of roof.
  • There will be normal construction noise during coating and clean-up.

Week of August 19th

Project Activities Impact
OE2 Move Out and Demo
  • Site utility cut / cap demolition
  • Site demolition
  • Potential Building heavy demolition
  • Underground electrical
  • Temporary pedestrian walkway from Lot I to Lot H.
  • Bookstore deliveries will be coordinated with M&O.
  • Goal is to have majority of heavy demolition of the OE2 building completed prior to the start of the fall semester.
  • On-going noise will be kept to a minimum.
  • Trucks will not be allowed on Campus Drive this week because of start of semester traffic.
  • New speed bumps on Campus Drive will take some getting used to…drive slowly.

OE1 Roofing Project

  • Clean-up
  • Punch list

Projected Completion Date: August 18, 2013

  • There will be minimal construction noise during punch corrections and clean-up.