Construction Update 7/25/2013

Week of July 29th

Project Activities: Impact:
OE2 Demo
  • Temporary speed bump striping
  • Irrigation Controller Relocation
  • Finalize temporary irrigation
  • Site utility cut / cap demolition
  • Site demolition
  • Building heavy demolition
  • Temporary pedestrian’s walkway from Lot I to Lot H.
  • Bookstore deliveries will be coordinated with M&O.
  • With heavy demolition of the existing OE2 building, there will be increased noise around this area. Trucks will also be on Campus Drive hauling demolition debris throughout the day.
  • The domestic water line will be SHUTDOWN to Bookstore, Bookstore Classroom and OE1 Building STARTING FRIDAY (8/2) 6am THRU SUNDAY (8/4) 5pm. Restrooms, sinks and drinking fountains will be off in these buildings only.
  • Temporary speed bumps will be striped early in the morning on Monday (7/29). Traffic control will be in place. Please proceed with caution in this area.
  • Due to speed bumps, reduced speeds are required.
OE1 Roofing Project
  • 30 day cure period
Projected Completion Date: August 18, 2013
  • OE1 Building opens to normal operations.

Week of August 5th

Project Activities: Impact:
OE2 Demo
  • Site utility cut / cap demolition
  • Site demolition
  • Building heavy demolition

  • Temporary pedestrian walkway from Lot I to Lot H.
  • Bookstore deliveries will be coordinated with M&O.
  • With heavy demolition of the existing OE2 building, there will be increased noise around this area. Trucks will also be on Campus Drive hauling demolition debris throughout the day.
  • Due to speed bumps, reduced speeds are required.
OE1 Roofing Project
  • 30 day cure period
Projected Completion Date: August 18, 2013
  • OE1 Building opens to normal operations.

Week of August 12th 

Project Activities: Impact:
OE2 Demo
  • Site utility cut / cap demolition
  • Site demolition
  • Building heavy demolition
  • Temporary pedestrian’s walkway from Lot I to Lot H.
  • Bookstore deliveries will be coordinated with M&O.
  • With heavy demolition of the existing OE2 building there will be increased noise around this area. Trucks will also be on Campus Drive hauling demolition debris throughout the day
  • Reduced speeds are required.
OE1 Roofing Project
  • Final roof coating (Sat & Sun)
  • Clean-up
  • Punch list
Projected Completion Date: August 18, 2013
  • Building ventilation will be off Sat & Sun during final coating of roof.
  • There will be normal construction noise during coating and clean-up.