Construction Update 7/18/2013

REMINDER:

With temporary speed bump installation A PORTION OF THE EAST END OF CAMPUS DRIVE WILL BE CLOSED THIS FRIDAY THRU SUNDAY (7/19 - 7/21). Access to campus via the east entrance will be via fire access road. Access to all parking lots will remain. All barricades will be removed Monday, 7/22, early morning. Also, contractor will be hauling dirt this Friday (7/19) and Saturday (7/20) from parking lot I to the dirt stockpile location. Majority of this dirt haul will be within section of east end of Campus Drive that will be closed, but traffic control will be in place from parking lot I to Aquatic Center parking lot.

Week of July 22nd 

Project Activities: Impact:
OE2 Demo
  • Partition installation within OE1 Building
  • Irrigation Controller Relocation
  • Site utility cut / cap demolition
  • Site demolition
  • Underground electrical installation
  • New speed bumps installed at apex east Campus Drive.
  • New construction entry to OE2 site.
Projected Completion Date: September 27, 2013
  • Temporary pedestrian’s walkway from Lot I to Lot H.
  • Bookstore deliveries will be coordinated with M&O.
  • Construction fencing has been installed.
  • Reduced speeds are required.
  • Addition construction traffic on east end of Campus.
OE1 Roofing Project
  • 30 day cure period
  • Metal wall panel and coping installation
Projected Completion Date: August 18, 2013
  • OE1 Building opens to normal operations.
  • Minimal construction noise due to hand tools

Week of July 29th

Project Activities: Impact:
OE2 Demo
  • Irrigation Controller Relocation
  • Site utility cut / cap demolition
  • Site demolition
  • Underground electrical installation
  • Building heavy demolition
Projected Completion Date: September 27, 2013
  • With heavy demolition of the existing OE2 building, there will be increased noise around this area. Trucks will also be on Campus Drive hauling demolition debris throughout the day.
  • Temporary pedestrian’s walkway from Lot I to Lot H.
  • Bookstore deliveries will be coordinated with M&O.
  • Do to speed bumps reduce speeds are required.
OE1 Roofing Project
  • 30 day cure period
Projected Completion Date: August 18, 2013
  • OE1 Building opens to normal operations.

Week of August 5th

Project Activities: Impact:
OE2 Demo
  • Site utility cut / cap demolition
  • Site demolition
  • Underground electrical installation
  • Building heavy demolition
Projected Completion Date: September 27, 2013
  • With heavy demolition of the existing OE2 building, there will be increased noise around this area. Trucks will also be on Campus Drive hauling demolition debris throughout the day.
  • Temporary pedestrian’s walkway from Lot I to Lot H.
  • Bookstore deliveries will be coordinated with M&O.
  • Do to speed bumps reduce speeds are required.
OE1 Roofing Project
  • 30 day cure period
Projected Completion Date: August 18, 2013
  • OE1 Building opens to normal operations.