Construction Update 7/11/2013

Week of July 15th

Project Activities: Impact:
OE2 Move Out and Demo
  • Partition installation within OE1 Building
  • Irrigation relocation
  • Site utility cut / cap and demolition
  • Site demolition
  • Underground electrical installation
  • Building hazardous material abatement
  • Construction entrance / exit build out
  • Temporary speed bump installation
Projected Completion Date: September 27, 2013
  • With installation of construction fencing a temporary walkway has been established from Lot I to Lot H.
  • A PORTION OF THE EAST END OF CAMPUS DRIVE WILL BE CLOSED NEXT FRIDAY THROUGH SUNDAY (7/19 - 7/21) for the installation of new speed bumps. Access to campus via the east entrance will be via fire access road. Access to all parking lots will remain. All barricades will be removed Monday, 7/22, early morning. No campus access to OE2 Bookstore deliveries to be coordinated with M&O.
OE1 Roofing Project
  • Complete wall panels
  • Punch list and clean-up
  • Demobilize
Projected Completion Date: August 18, 2013
  • There will be normal construction noise during installation of material.
  • OE1 Building to be opened to building occupants on Wednesday July 17.

Week of July 22nd

Project Activities: Impact:
OE2 Move Out and Demo
  • Site utility cut / cap demolition
  • Site demolition
  • Underground electrical installation
  • Building demolition - soft demolition within building
  • Site rough grading
Projected Completion Date: September 27, 2013
  • With construction fencing temporary walkway has been established from Lot I to Lot H.
  • Site rough grading construction activity will cause addition construction traffic on the upper east end of Campus Drive beginning on Friday 7/26 and into the weekend. Please proceed with caution in this area.
OE1 Roofing Project
  • 30 day cure period
Projected Completion Date: August 18, 2013
  • OE1 Building open to normal operations.

Week of July 29th

Project Activities: Impact:
OE2 Move Out and Demo
  • Site utility cut / cap demolition
  • Site demolition
  • Underground electrical installation
  • Building heavy demolition
  • Site rough grading
Projected Completion Date: September 27, 2013
  • With construction fencing temporary walkway has been established from Lot I to Lot H.
  • With heavy demolition of the existing OE2 building there will be increased noise around this area.
  • Site rough grading construction activity will see construction traffic on Campus Drive on the upper east end of Campus Drive Friday 8/2 and into the weekend. Please proceed with caution in this area.
OE1 Roofing Project
  • 30 day cure period
Projected Completion Date: August 18, 2013
  • OE1 Building open to normal operations.