We will make every effort to assure the accuracy and completeness of these updates; however, there will be some changes and adjustments as construction progresses.

HOW WILL CONSTRUCTION ACTIVITY AFFECT YOU?

  • Construction personnel and equipment will be on campus drive periodically throughout construction. Please proceed with caution.
  • Beginning July 7th, the central-half of Campus Drive (from parking lot D to parking lot H) is closed to vehicular and pedestrian traffic. Use parking lot C as the vehicular turn around point for the west-end of Campus Drive. Use parking lot H as the vehicular turn around point for the east-end of Campus Drive
  • Parking lots open: CDC, A1, A, B, C, H, and the Aquatic Center.
  • Parking lots closed: D, E, F, G, I, and overflow.
  • To access the west-end of campus, park in CDC, A1, A, B, or C parking lots. To access the east-end of campus, park in H or the Aquatic Center parking lots.
  • For vehicular access behind the OE complex and Bookstore there is temporary access through parking lot I to the OE access road.
  • There is a new temporary pathway/walkway for pedestrian access to and from the west-end and east-end of campus along the north side of Campus Drive during the construction work within the central-half of Campus Drive. All other pedestrian access across campus will remain in its current condition. (Map of temporary pathway/walkway)
  • Access to the tennis courts is from the south gates.
  • Access to soccer field is routed via the walkway south and west of the tennis courts. This route will continue for the duration of the MSA project.
  • Work in future IDF data room on the lower level of the LADM is ongoing. Work with extreme noise levels will be coordinated with CHC campus operations in an effort to minimize disruption.
  • Work in and around manholes throughout campus will be ongoing for the data relocation portion of the library demolition project. Full safety measures will be exercised for this operation. Please proceed with caution.
  • Temporary fencing around old library demolition project site will be in-place. West-half of the main quad and pathway’s/walkway’s directly north and south of the old library will be closed.

Week of July 11th

Parking, ADA Access & Lighting Improvements (PAL)

Campus wide

  • Trenching, forming and pouring of light pole bases and electrical wiring
  • Sewer line installation north of Campus Drive up hill to M&O
  • Lowering of Southern California Edison vault on west-end of Campus Drive

Lot A – Parking Lot A

  • Punch list work

Lot B – Parking Lot B

  • Punch list work

Lot C – Parking Lot C

  • Punch list work
  • Form & pour flatwork, stairs and ADA accessible ramps
  • Landscape installation

Lot D – Parking Lot D

  • AC pavement demolition

Lot E – Parking Lot E

  • Due to closure of central-half of Campus Drive (from parking lot D to parking lot H) parking lot E is closed for vehicular use.

Lot F – Parking Lot F

  • AC pavement installation
  • Form & pour flatwork, stairs and ADA accessible ramps
  • Landscape installation

Lot G – Parking Lot G

  • AC pavement installation
  • Grading and forming for electrical equipment enclosure
  • Form & pour flatwork, stairs and ADA accessible ramps
  • Landscape installation

Lot H – Parking lot H

  • Form & pour flatwork, stairs and ADA accessible ramps
  • Landscape installation

Lot I – Parking lot I

  • Grading and forming for electrical equipment enclosure
  • Sub-grade preparation

Campus Drive (Central-half)

  • AC pavement demolition

Math and Science Annex (MSA)

  • Grading and forming for flatwork
  • Irrigation piping installation
  • Math Modular buildings: interior finishes
  • Science Modular buildings: interior finishes and roofing installation

Old Library Demolition

Data Relocation

  • Contractor will be working in and around various manholes throughout campus pulling out old wiring

Library Demolition

  • Temporary fencing around project site will be in-place

Week of July 18th

Parking, ADA Access & Lighting Improvements (PAL)

Campus wide

  • Trenching, forming and pouring of light pole bases and electrical wiring
  • Sewer line installation north of Campus Drive up hill to M&O

Lot A – Parking Lot A

  • Punch list work

Lot B – Parking Lot B

  • Punch list work

Lot C – Parking Lot C

  • Punch list work
  • Form & pour flatwork, stairs and ADA accessible ramps
  • Landscape installation

Lot D – Parking Lot D

  • AC pavement demolition
  • Sub-grade preparation

Lot E – Parking Lot E

  • Due to closure of central-half of Campus Drive (from parking lot D to parking lot H) parking lot E is closed for vehicular use.

Lot F – Parking Lot F

  • Form & pour flatwork, stairs and ADA accessible ramps
  • Landscape installation

Lot G – Parking Lot G

  • Grading and forming for electrical equipment enclosure
  • Form & pour flatwork, stairs and ADA accessible ramps
  • Landscape installation

Lot H – Parking lot H

  • Form & pour flatwork, stairs and ADA accessible ramps
  • Landscape installation

Lot I – Parking lot I

  • Grading and forming for electrical equipment enclosure
  • Aggregate base installation

Campus Drive (Central-half)

  • AC pavement demolition
  • Sub-grade preparation

Math and Science Annex (MSA)

  • Grading and forming for flatwork
  • Math Modular buildings: interior finishes and pull main electrical feeders & wiring
  • Science Modular buildings: interior finishes and pull main electrical feeders & wiring

Old Library Demolition

Data Relocation

  • No work scheduled

Library Demolition

  • Temporary fencing around project site will be in-place

NOTICE: CENTRAL-HALF OF CAMPUS DRIVE, PARKING LOT D & PARKING LOT E CLOSURE BEGINNING TOMORROW, JULY 7:

Beginning tomorrow morning, July 7, the central-half of Campus Drive (from parking lot D to parking lot H) will be closed to vehicular traffic.

Construction crews are setting up temporary fencing in preparation for these closures; please proceed with caution during this transition.

This closure will bring about the following changes:

Roadway, Parking Lot and Pedestrian Access Map

PARKING LOTS OPEN:

  • Parking lots CDC, A1, A, B, C, H, and the Aquatic Center will remain open.
  • To access to the west-end of campus, park in CDC, A1, A, B, or C.
  • To access to the east-end of campus, park in H or the Aquatic Center parking lot.
  • For vehicular access behind the OE complex and Bookstore there is temporary access through parking lot I to the OE access road.

PARKING LOTS CLOSED:

  • Parking lots D, E, F, G, I, and overflow will be closed

PEDESTRIAN ACCESS:

  • There is a new temporary pathway/walkway for Pedestrian access to and from the west-end and east-end of campus along the north side of Campus Drive during the construction work within the central-half of Campus Drive.
  • All other pedestrian access across campus will remain in its current condition.

CENTRAL-HALF OF CAMPUS DRIVE CLOSED:

  • Campus Drive from parking lot D to parking lot H will be closed to vehicular traffic.
  • Use parking lot C as the vehicular turn around point for the west-end of Campus Drive.
  • Use parking lot H as the vehicular turn around point for the east-end of Campus Drive.
  • See graphic attachment for further detail.

We appreciate your cooperation during construction. Inconvenience from the construction is being minimized as much as possible.

We will all share in a safer and more accessible Crafton Hills College campus once the Parking Lot / ADA / Lighting Improvement construction is completed.

Thank you.