Construction Update 7-3-2013

Week of July 8th

Project Activities:

Impact:

OE2 Move Out and Demo

 

  • Irrigation relocation
  • Clear site
  • Site utility cut / cap and demolition
  • Site demolition
  • Underground electrical installation
  • Building hazardous material abatement
  • Construction entrance / exit build out

Projected Completion Date: September 27, 2013

  • With installation of construction fencing a temporary walkway has been established from Lot I to Lot H.
  • No campus access to OE2 interior do to hazardous material abatement.

OE1 Roofing Project

 

  • Ongoing roofing installation.

Projected Completion Date: August 18, 2013

  • Due to the shutdown of the building ventilation, OE1 building will be closed for the duration of the project.
  • There will be normal construction noise during installation of material. There will be a tar smell from the project during hot asphalt placement.
  • Limited access by CHC staff, extra caution is warranted within temporary fencing.

Week of July 15th

Project Activities:

Impact:

OE2 Move Out and Demo

 

  • Site utility cut / cap and demolition
  • Site demolition
  • Underground electrical installation
  • Building hazardous material abatement
  • Construction entrance / exit build out
  • Temporary speed bump installation at apex of east Campus Drive

Projected Completion Date: September 27, 2013

  • Construction fencing a temporary walkway has been established from Lot I to Lot H
  • On Friday, 7/19 traffic control will be in place for temporary speed bump installation at the apex of east Campus Drive.

OE1 Roofing Project

 

  • Minor roofing work to continue

Projected Completion Date: August 18, 2013

  • There will be normal construction noise during installation of material.
  • OE1 Building to be reopened to campus staff and temporary fence will be removed.

Week of July 22nd

Project Activities:

Impact:

OE2 Move Out and Demo

 

  • Site utility cut / cap demolition
  • Site demolition

Projected Completion Date: September 27, 2013

  • Underground electrical installation
  • Building demolition - soft demolition within building
  • Installation of construction fencing a temporary walkway has been established from Lot I to Lot H.
  • New speed bumps at apex of east Campus Drive.

OE1 Roofing Project

 

  • 30 day cure period.
  • Minor roofing work to continue.

Projected Completion Date: August 18, 2013

  • OE1 Building opens to normal operations.