Construction Update 6/27/2013

Week of July 1st

Project Activities: Impact:
Electrical Reroute:
  • Punch list and cleanup
  • Complete
  • No impact to pedestrian walkways
  • No construction noise.

OE2 Move Out and Demo

  • Irrigation relocation
  • Site utility demolition
  • Site clear and grub
  • Construction entrance / exit build out
  • Begin activity within building: soft demolition, etc.
  • With installation of construction fencing a temporary walkway has been established to/from Lot I.
  • Bookstore deliveries to be coordinated with M&O.

OE1 Roofing Project

  • Continue removing existing roofing
  • Continue installation of new roof

Projected Completion Date: July 15th, 2013

  • Due to the shutdown of the building ventilation, OE1 building will be closed for the duration of the project.
  • There will be minimal construction noise during removal and disposal of existing roofing material.
  • There will be a tar smell from the project during hot asphalt placement.

SSB 1st Floor Painting and Flooring Project

  • Complete

Week of July 8th

Project Activities: Impact:

OE2 Move Out and Demo

  • Irrigation relocation
  • Site utility demolition
  • Site demolition
  • Construction entrance / exit build out
  • Underground electrical installation
  • Building hazardous material abatement
  • With installation of construction fencing a temporary walkway has been established to/from Lot I.
  • Bookstore deliveries to be coordinated with M&O.

OE1 Roofing Project

  • Complete roof
  • Punch list and clean-up

Projected Completion Date: July 15th, 2013

  • Due to the shutdown of the building ventilation, OE1 building will be closed for the duration of the project.
  • There will be minimal construction noise during removal and disposal of existing roofing material.
  • There will be a tar smell from the project during hot asphalt placement.

Week of July 15th

Project Activities: Impact:

OE2 Move Out and Demo

  • Site utility demolition
  • Site demolition
  • Underground electrical installation
  • Building hazardous material abatement
  • With installation of construction fencing a temporary walkway has been established to/from Lot I.
  • Bookstore deliveries to be coordinated with M&O.

OE1 Roofing Project

  • Demobilize
  • Complete

Projected Completion Date: July 15th, 2013

  • OE1 Building to be reopened.