Construction Update 6/10/2013

Week of June 10th

Project: Impact:

Electrical Reroute

  • Site restoration
  • Cable and equipment installation
  • Electrical shutdown/connection - CHS

Projected Completion Date: June 30th, 2013

  • Pedestrians will be detoured to/from the LRC and the 1st floor of the CHS building. Zoom in on the attached map for pedestrian detours.
  • There will be minimal construction noise.

OE2 Move Out and Demo

  • Pre-construction activities
  • Demolition mobilization to begin 6/17
  • No projected impact this week.

SSB 1st Floor Painting and Flooring Project

  • Painting

Projected completion date: June 27, 2013

  • HWC will be temporarily located at the Gym (NW office area)
  • DSPS will be temporarily located in the LRC

Week of June 17th

Project: Impact:

Electrical Reroute

  • Cable and equipment installation
  • Electrical shutdown/connection
  • Phone/data shutdown (tentative)
Projected Completion Date: June 30th, 2013
  • Pedestrians will be detoured to/from the LRC and the 1st floor of the CHS building. Zoom in on the attached map for pedestrian detours.
  • There will be minimal construction noise for concrete demolition and concrete placement.
  • Electrical shutdown scheduled for Thursday, June 20th (6pm) –Sunday, June 23rd (will affect PAC, SSA, Cafeteria, SSB, and CDC)
  • Electrical shutdown on Saturday, June 23rd (will affect CHS and LADM Physics and Anatomy labs). Coordination with affected areas is in process.
  • Phone/data shutdown scheduled for Friday, June 21nd -Sunday, June 23rd (will affect PAC)
  • Phone/data shutdown scheduled for Saturday, June 22nd (will affect CHS)

OE2 Demo

  • Install temp. pedestrian walkway from Lot I
  • Install construction fencing and signage
  • Fencing will be installed and detour pedestrians by alternate route to/from Lot I.

SSB 1st Floor Painting and Flooring Project

  • Install flooring

Projected completion date: June 27, 2013

  • HWC temporarily located at the Gym
  • DSPS temporarily located in the LRC

Week of June 24th

Project: Impact:

Electrical Reroute

  • Punch list and cleanup

Projected Completion Date: June 30th, 2013

  • Pedestrians will be detoured to/from the LRC and the 1st floor of the CHS building. See fencing map for pedestrian detours.
  • Sidewalks reopened

OE2 Demo

  • Continue installation fencing, signage, walkways, etc.
  • Irrigation relocation
  • Fencing will be installed and detour pedestrians by alternate route to/from Lot I.

SSB 1st Floor Painting and Flooring Project

  • Re-install furniture and set up areas

Projected completion date: June 27, 2013

  • HWC and DSPS moved back into SSB