Crafton Hills College Construction Update 5/16/11:

We will make every effort to assure the accuracy and completeness of these updates; however, there will be some changes and adjustments as construction progresses.

HOW WILL CONSTRUCTION ACTIVITY AFFECT YOU?

  • Construction personnel and equipment will be on campus drive periodically throughout construction. Please proceed with caution.
  • The Temporary parking lot (gravel lot near Lot A) is open as an overflow “day use only” lot. Pedestrian access to campus is the designated striped walkway along the southern side of campus drive.
  • Parking Lots C & H are closed to staff and students.
  • With parking lot C being closed, temporary staff parking stalls are currently located in parking lot B & E to compensate for the lost stalls. See the construction notice email sent out previously for further information.
  • Access to the tennis courts is from the south gates.
  • Access to soccer field is routed via the walkway south and west of the tennis courts. This route will continue for the duration of the MSA project.
  • Parking spaces/stalls on campus drive adjacent to the MSA project site are closed to staff and students.
  • Tree demolition will be taking place throughout the campus (majority of work will be in and around parking lots). While this operation is taking place a few parking stalls will be closed down from time to time. Full safety measures will be exercised for this operation. Please proceed with caution.
  • Work in and around manholes throughout campus will be ongoing for the data relocation portion of the library demolition project. Full safety measures will be exercised for this operation. Please proceed with caution.
  • Modular buildings that are currently located in parking lot I will be installed at the MSA project site the week of May 16th. Large hauling equipment will be used in this operation. Full safety measures will be exercised for this operation. Please proceed with caution.

Week of May 16th

Parking, ADA Access & Lighting Improvements (PAL)

Campus wide (majority of work in and around parking lots)

  • Tree demolition
  • Clear & grub
  • Trenching, forming and pouring of light pole bases and electrical wiring

Lot A – Parking Lot A

  • Punch list work

Lot B – Parking Lot B

  • Punch list

Lot C – Parking Lot C

  • Aggregate base installation
  • Form & pour flatwork
  • Landscape installation

Lot H – Parking Lot H

  • Trenching and installation for irrigation piping and electrical conduit
  • Asphalt demolition

Math and Science Annex (MSA)

  • Rough grading around modular building footprint
  • Trenching and installation for underground building utilities
  • Modular building fabrication
  • Modular building installation for math classrooms

Old Library Demolition

Data Relocation

  • Contractor will be working in and around various manholes throughout campus
  • Contractor will be working in the basement of the old library and various IDFs throughout campus
  • LADM & LRC IDF room preparation and work

Week of May 23th

Parking, ADA Access & Lighting Improvements (PAL)

Campus wide (majority of work in and around parking lots)

  • Tree demolition
  • Clear & grub
  • Trenching, forming and pouring of light pole bases and electrical wiring

Lot A – Parking Lot A

  • Punch list work

Lot B – Parking Lot B

  • Punch list work

Lot C – Parking Lot C

  • Asphalt pavement installation
  • Slurry & striping
  • Form & pour flatwork
  • Handrail installation
  • Landscape installation

Lot H – Parking Lot H

  • Trenching and installation for irrigation piping and electrical conduit
  • Sub grade preparation
  • Aggregate base installation

Math and Science Annex (MSA)

  • Rough grading around modular building footprint
  • Trenching and installation for underground building utilities
  • Modular building fabrication
  • Modular building installation for math classrooms

Old Library Demolition

Data Relocation

  • Contractor will be working in and around various manholes throughout campus
  • Contractor will be working in the basement of the old library and various IDFs throughout campus
  • LADM & LRC IDF room preparation and work

NOTICE: MODULAR CLASSROOM BUILDINGS BEING DELIVERED TO CHC CAMPUS

Temporary location of MSA buildings 

  • Project: Math & Science Annex (MSA)
  • Six segments of the math classroom modular buildings are being delivered to the CHC campus this Thursday, May 12th and Friday, Mat 13th.
  • They will be temporarily located in the north section of parking lot I. Delineators and caution tape was set-up the morning of Wednesday, May 11th to ensure this area was designated.
  • The six segments will be moved from there temporary location in parking lot I to the MSA project site the week of May 16th.
  • Large hauling equipment will be used in this operation. Full safety measures will be exercised for this operation. Please proceed with caution.

We appreciate your cooperation during construction. Please know that impacts as a result of construction are being discussed constantly and being kept to as minimal as possible.

Thank you.