Crafton Hills College Construction Update 5/9/11:

We will make every effort to assure the accuracy and completeness of these updates; however, there will be some changes and adjustments as construction progresses.

HOW WILL CONSTRUCTION ACTIVITY AFFECT YOU?

  • Construction personnel and equipment will be on campus drive periodically throughout construction. Please proceed with caution.
  • The Temporary parking lot (gravel lot near Lot A) is open as an overflow “day use only” lot. Pedestrian access to campus is the designated striped walkway along the southern side of campus drive.
  • Parking Lots C & H are closed to staff and students.
  • With parking lot C being closed, temporary staff parking stalls are currently located in parking lot E to compensate for the lost stalls and will be located in parking lot B tentatively scheduled for May 2nd. See the construction notice email sent out previously for further information.
  • Access to the tennis courts is from the south gates.
  • Access to soccer field is routed via the walkway south and west of the tennis courts. This route will continue for the duration of the MSA project.
  • Parking spaces/stalls on campus drive adjacent to the MSA project site are closed to staff and students.
  • Tree demolition will be taking place throughout the campus (majority of work will be in and around parking lots). While this operation is taking place a few parking stalls will be closed down from time to time. Full safety measures will be exercised for this operation. Please proceed with caution.
  • Work in and around manholes throughout campus will be ongoing for the data relocation portion of the library demolition project. Full safety measures will be exercised for this operation. Please proceed with caution.

Week of May 9th

Parking, ADA Access & Lighting Improvements (PAL)

Campus wide (majority of work in and around parking lots)

  • Tree demolition
  • Clear & grub
  • Trenching, forming and pouring of light pole bases and electrical wiring

Lot A – Parking Lot A

  • Punch list work

Lot B – Parking Lot B

  • Punch list

Lot C – Parking Lot C

  • Sub grade preparation
  • Form & pour flatwork
  • Landscape installation

Lot H – Parking Lot H

  • Survey and preparation work
  • Trenching and installation for irrigation piping and electrical conduit
  • Asphalt demolition

Math and Science Annex (MSA)

  • Modular building fabrication
  • Trenching and installation for underground building utilities

Old Library Demolition

Data Relocation

  • Contractor will be working in and around various manholes throughout campus
  • Contractor will be working in the basement of the old library and various IDFs throughout campus
  • LADM & LRC IDF room preparation and work

Week of May 16th

Parking, ADA Access & Lighting Improvements (PAL)

Campus wide (majority of work in and around parking lots)

  • Tree demolition
  • Clear & grub
  • Trenching, forming and pouring of light pole bases and electrical wiring

Lot A – Parking Lot A

  • Punch list work

Lot B – Parking Lot B

  • Punch list work

Lot C – Parking Lot C

  • Subgrade preparation
  • Aggregate base installation
  • Form & pour flatwork
  • Landscape installation

Lot H – Parking Lot H

  • Trenching and installation for irrigation piping and electrical conduit
  • Asphalt demolition

Math and Science Annex (MSA)

  • Fine grading around modular building footprint
  • Modular building fabrication
  • Trenching and installation for underground building utilities

Old Library Demolition

Data Relocation

  • Contractor will be working in and around various manholes throughout campus
  • Contractor will be working in the basement of the old library and various IDFs throughout campus
  • LADM & LRC IDF room preparation and work

NOTICE: PARKING LOT H CLOSED AND PARKING LOT B OPEN ON MONDAY, MAY 2nd

  • Lot B will be open on Monday, May 2nd along with the new stairway from Lot’s A & B to the Cafeteria quad.
  • On Monday, May 2nd, Parking Lot H will be closed to staff and students.
  • Lot C is still under construction and is scheduled to reopen around the start of summer school.
  • As mentioned previously, with the closure of parking lot C, staff parking stalls have been added in Parking Lot E to compensate for the lost stalls.
  • Originally the plan was to also provide staff parking stalls in Parking Lot B when it reopened, but after evaluating how the staff parking stalls in Parking Lot E are being utilized we believe that the staff parking stalls in Parking Lot B aren’t necessary.
  • See site plans showing locations of temporarily relocated staff parking stalls in both Parking Lot E.
  • Temporarily relocated staff parking stalls will be clearly identified and policed.
  • Temporarily relocated staff parking stalls will be labeled Staff Parking Only Until 5:00 PM.

We appreciate your cooperation during construction. Please know that impacts as a result of construction are being discussed constantly and being kept to as minimal as possible. Also know that the end result once construction is completed on the Parking Lot / ADA / Lighting Improvement project is a safer and more accessible Crafton Hills College campus!!!

Thank you.