NOTICE: PARKING LOT C CLOSED AND PARKING LOT A OPEN ON MONDAY, APRIL 18TH

  • Lot A will be open on Monday, April 18th along with the new stairway from Lot A to the Cafeteria quad.
  • On Monday, April 18th, Parking Lot C will be closed to staff and students.
  • Lot B is still under construction and is scheduled to reopen around May 2nd. Thus, the closure of Lots B and C will overlap for approximately 2 weeks.
  • With the closure of parking lot C, staff parking stalls will be added in Parking Lot E to compensate for the lost stalls.
  • When Parking Lot B reopens, the east row of Lot B will be designated as temporary staff parking until Lot C is completed.
  • See site plans showing locations of temporarily relocated staff parking stalls in both parking lots E & B.
  • Temporarily relocated staff parking stalls will be clearly identified and policed. District Police will be in Lot E on Monday morning to provide direction and information to staff and students.
  • Temporarily relocated staff parking stalls will be labeled Staff Parking Only Until 5:00 PM.

We appreciate your cooperation during construction. Please know that impacts as a result of construction are being discussed constantly and being kept to as minimal as possible. Also know that the end result once construction is completed on the Parking Lot / ADA / Lighting Improvement project is a safer and more accessible Crafton Hills College campus!!!

Crafton Hills College Construction Update 4/14/11:

We will make every effort to assure the accuracy and completeness of these updates; however, there will be some changes and adjustments as construction progresses.

HOW WILL CONSTRUCTION ACTIVITY AFFECT YOU?

  • Construction personnel and equipment will be on campus drive periodically throughout construction. Please proceed with caution.
  • The Temporary parking lot (gravel lot near Lot A) is open as an overflow “day use only” lot. Pedestrian access to campus is the designated striped walkway along the southern side of campus drive.
  • Parking Lots A & B are closed to staff and students.
  • Access to the tennis courts is from the south gates.
  • Access to soccer field is routed via the walkway south and west of the tennis courts. This route will continue for the duration of the MSA project.
  • Parking spaces/stalls on campus drive adjacent to the MSA project site are closed to staff and students.
  • Tree demolition will be taking place throughout the campus (majority of work will be in and around parking lots). While this operation is taking place a few parking stalls will be closed down from time to time. Full safety measures will be exercised for this operation.

Week of April 11th

Parking, ADA Access & Lighting Improvements (PAL)

Campus wide (majority of work in and around parking lots)

  • Tree demolition
  • Clear & grub

Lot A – Parking Lot A

  • Sack and patch flatwork
  • Landscape installation
  • Handrail installation
  • Clean-up
  • Punch list

Lot B – Parking Lot B

  • Asphalt paving
  • Form and pour flatwork
  • Landscape installation

Math and Science Annex (MSA)

  • Form and pour concrete for footings and foundations for modular classrooms
  • Modular building fabrication

Week of April 18th

Parking, ADA Access & Lighting Improvements (PAL)

Campus wide (majority of work in and around parking lots)

  • Tree demolition
  • Clear & grub

Lot A – Parking Lot A

  • Clean-up
  • Punch list
  • Temporary lighting set-up/installation
  • TENATIVE DATE FOR PARKING LOT A TURNOVER

Lot B – Parking Lot B

  • Asphalt paving
  • Striping
  • Form & pour and sack & patch flatwork
  • Landscape installation
  • Handrail installation

Math and Science Annex (MSA)

  • Strip forms and backfill around footings and foundations for modular classrooms
  • Modular building fabrication