Week of August 30

Project Activities:

Impact:

New Science Building (Canyon Halls (CYN)):

  • Arrival of metal cabinets and fume hoods

at the Lab Wing Building

  • Continue the installation for Firestone Panels east and West at Laboratory Wing Building
  • Install elevator guard rails, cab doors & controls
  • mechanical room at Lab Wing Building at the Lab Wing Building
  • Install ceramic tile in walls in restrooms on 2nd floor at Lab Wing Building
  • Complete above ceiling seismic work at Lab Wing Building
  • Complete above ceiling seismic work at Lab Wing Building

 

  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

 

OE2 Building (Public Safety & Allied Health Complex (PSAH)):

  • Exterior Aluminum Fin installation
  • Metal panel installation
  • Pedestal paver installation at corridors
  • Decomposed granite installation
  • Landscaping/Hardscaping
  • Testing, adjusting and balancing
  • Punchlist on 1st floor
  • FF&E installation

 

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.
  • Delivery trucks/ increased traffic.

Crafton Center (CCR):

  • Cement panels
  • Metal panels
  • Fixed sun screens
  • Exterior coping/flashing
  • Casework at Concourse
  • Operable Partitions
  • Access Doors
  • AV Racks
  • Final Paint
  • Fire Extinguisher Cabinets
  • Marker boards/Tack boards
  • Window Coverings
  • Signage
  • Carpet & Linoleum
  • Commissioning
  • Test Electrical, Low Voltage & Fire Alarm
  • Test & Balance HVAC
  • Prep & Pour Topping Slab at Balcony
  • Prep & Pour Storage Yard Slab
  • Light Pole Bases & Lights
  • Form Sidewalks at Parking Lot C
  • Form Sidewalks at North and West
  • Irrigation distribution

 

  • Access to Parking Lot B is from the west stairs only.  Stairs connecting Parking Lot B and C is CLOSED.
  • Pedestrian path of travel around project site will be marked with signage.
  • Increase in Construction noise from on-site demolition activity.
  • Delivery and Haul-off trucks/ increased traffic.  Proper traffic control will be provided.

Wayfinding

  • Locating and staking area where the new footing will go.
  • Continue the refurbishment of parking monuments.
  • Dig footings
  • Removal of parking lot monument A, K, L

 

  • No traffic impact, contractor will use golf cart to decrease impact on campus traffic.  

PE Complex

  • Fabrication of screen Wall

 

  • No traffic impact

Week of September 6

Project Activities:

Impact:

New Science Building (Canyon Halls (CYN)):

  • Installation of metal cabinets and fume hoods at Lab Wing Building
  • Install and make up equipment in mechanical room at Lab Wing Building
  • Continue the installation for Firestone Panels East and West at Laboratory Wing Building at Lab Wing Building
  • Continuing the Installation of the  elevator guard rails, cab doors & controls
  • Complete above ceiling seismic work at Lab Wing Building
  • Complete grading & export soil at the south slope at the Lab Wing Building
  • Continue the installation of light fixtures, ceiling registers, EMS, FA & speakers at the lab Wing Building

 

  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

 

OE2 Building (Public Safety & Allied Health Complex (PSAH)):

  • Exterior Aluminum Fin installation
  • Metal panel installation
  • Decomposed granite installation
  • Landscaping/Hardscaping
  • Testing, adjusting and balancing
  • Punchlist on 2nd floor
  • FF&E installation

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.
  • Delivery trucks/ increased traffic.

Crafton Center (CCR):

  • Cement panels
  • Metal panels
  • Exterior coping/flashing
  • Exterior Electrical Fixtures and Trim
  • Casework at Concourse
  • Folding Grills
  • Final Paint
  • Marker boards/Tack boards
  • Window Coverings
  • Commissioning
  • Test & Balance HVAC
  • Cold Plane Asphalt Parking Lot C
  • Asphalt Paving Parking Lot C
  • Pour Sidewalks at Parking Lot C
  • Pour Sidewalks at North and West
  • Pavers
  • Irrigation distribution
  • Landscaping

 

  • Access to Parking Lot B is from the west stairs only.  Stairs connecting Parking Lot B and C is CLOSED.
  • Pedestrian path of travel around project site will be marked with signage.
  • Increase in Construction noise from on-site demolition activity.
  • Delivery and Haul-off trucks/ increased traffic.  Proper traffic control will be provided.

PE Complex

  • Installation of the Screen Wall on the PE complex Roof

 

  • Parking impact due to contractor on site.
  • Minimal Construction Noise due to installation of Screen Walls.

Wayfinding

  • Continue Digging Footings
  • Paint Parking Monuments. Painting is to be done at shop.
  • No traffic impact, contractor will use golf cart to decrease impact on campus traffic.  

Week of September 13

Project Activities:

Impact:

New Science Building (Canyon Halls (CYN)):

  • Grading for the site concrete entrance of the fire lane
  • Installation of metal cabinets and fume hoods at Lab Wing Building
  • Complete above ceiling seismic work at Lab Wing Building
  • Continue the installation of light fixtures, ceiling registers, EMS, FA & speakers at the Lab Wing Building
  • Continue the installation for Firestone Panels East and West at Laboratory Wing Building at Lab Wing Building

 

  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

 

OE2 Building (Public Safety & Allied Health Complex (PSAH)):

  • Exterior Aluminum Fin installation
  • Landscaping/Hardscaping
  • Testing, adjusting and balancing
  • Punchlist on 2nd floor

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.
  • Delivery trucks/ increased traffic.

Crafton Center (CCR):

  • Cement panels
  • Exterior coping/flashing
  • Exterior Electrical Fixtures and Trim
  • Final Clean
  • Contractors Punchlist
  • Commissioning
  • Asphalt Paving Parking Lot C
  • Striping Parking Lot C
  • Railings at Parking Lot C
  • Pavers
  • Landscaping

 

  • Access to Parking Lot B is from the west stairs only.  Stairs connecting Parking Lot B and C is CLOSED.
  • Pedestrian path of travel around project site will be marked with signage.
  • Increase in Construction noise from on-site demolition activity.
  • Delivery and Haul-off trucks/ increased traffic.  Proper traffic control will be provided.

PE Complex

  • None

 

  • None

Wayfinding

  • Pour Footings.
  • Install Parking monuments.
  • Minimal impact to parking lots due to installation of parking monuments.