Week of October 12

Project Activities:

Impact:

PE Complex

  • Closeout documents
  • Performing punch list items
  • None at this time.

New Science Building

  • Continue welding for structural steel Lab Wing building
  • Continue to shake out & weld metal decking for Lab Wing building
  • Layout and install inserts for MEP, on the 2nd floor metal decking at Lab Wing Building
  • Continue with UG plumbing RI. As required at the Lab Wing Building
  • Forming, install rebar & pour concrete on GL/L1, LF to LC at Lab Wing Building
  • Continue to install & weld off metal decking, closure angles & install nelson studs at the roof at Lab Wing Building
  • Bolt up and welding structural steel Lecture Wing Building
  • Re-mobilize & complete steel erection at Lecture Wing welding
  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

OE2 Building

  • West wing 2nd level slab preparation and rebar installation
  • West wing exterior framing
  • West wing exterior sheathing
  • West wing 1st floor interior framing
  • West wing 1st floor door frame installation
  • West wing 1st floor rough overhead MEP installation
  • East wing framing preparation
  • West & east wing roofing
  • HSS support steel erection
  • Drill yard site wall forming & rebar
  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.

Crafton Center

  • Welding of steel connections
  • Metal deck welding
  • Continue rebar installation at grade beams GL 5-9
  • Pour grade beams GL 5-9
  • Rebar installation at grade beams GL 9-13 starts
  • Form and grade slab on grade GL 1-4
  • Backfill elevator walls
  • Backfill at Parking Lot C walls
  • Form curb and gutter in Parking Lot C
  • Pour curb and gutter at Parking Lot C walls
  • Parking Lot C will be CLOSED through the duration of the project.
  • Access to Parking Lot B is from the west stairs only.  Stairs connecting Parking Lot B and C is CLOSED.
  • Temporary pedestrian path of travel around project site marked with signage.
  • Construction noise from on-site activity.
  • Delivery trucks/ increased traffic.  Proper traffic control will be provided.

Week of October 19

Project Activities: Impact:

PE Complex

  • Closeout documents
  • Performing punch list items
  • None at this time.

New Science Building

  • Install slab on deck rebar 2nd floor at Lab Wing Building
  • Continue forming, install rebar & pour concrete on GL/L1, LF to LC at Lab Wing Building
  • Cure time & strip forms from the GL/L1 wall pour at the Lab Wing Building
  • Continue to install metal decking for roof at Lab Wing Building
  • Install UG plumbing RI at the first floor level at the Lab Wing Building
  • Install UG electrical RI at the 1st floor level at the Lab Wing Building
  • Install shoring for the exterior walkway GL/L8 to L9
  • Continue to bolt up and welding structural steel Lecture Wing Building
  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

OE2 Building

  • West wing 2nd level slab preparation and rebar installation
  • West wing exterior sheathing
  • West wing 1st floor interior framing
  • West wing 1st floor rough overhead MEP installation
  • East wing exterior & interior framing
  • West & east wing roofing
  • HSS support steel erection
  • Drill yard site wall forming & rebar
  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.

Crafton Center

  • Welding of steel connections
  • Metal deck welding
  • Pour grade beams GL 9-13
  • Pour slab on grade GL 1-4
  • Form and grade slab on grade GL 4-8
  • Landscape irrigation in Parking Lot C
  • Parking Lot C will be CLOSED through the duration of the project.
  • Access to Parking Lot B is from the west stairs only.  Stairs connecting Parking Lot B and C is CLOSED.
  • Temporary pedestrian path of travel around project site marked with signage.
  • Construction noise from on-site activity.
  • Delivery trucks/ increased traffic.  Proper traffic control will be provided.

Week of October 26

Project Activities: Impact:

PE Complex

  • Closeout documents
  • Performing punch list items
  • None at this time.

New Science Building

  • Install slab on deck rebar 2nd floor at Lab Wing Building
  • Continue forming, install rebar & pour concrete on GL/L1, LF to LC at Lab Wing Building
  • Cure time & strip forms from the GL/L1 wall pour at the Lab Wing Building
  • Continue to install metal decking for roof at Lab Wing Building
  • Install UG plumbing RI at the first floor level at the Lab Wing Building
  • Install UG electrical RI at the 1st floor level at the Lab Wing Building
  • Install shoring for the exterior walkway GL/L8 to L9
  • Continue to bolt up and welding structural steel Lecture Wing Building
  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

OE2 Building

  • West wing 2nd floor concrete pour currently scheduled for 10-27-2014.
  • West wing exterior sheathing
  • West wing 1st floor interior framing
  • West wing 1st floor rough overhead MEP installation
  • East wing exterior & interior framing
  • West & east wing roofing
  • Drill yard site wall forming & rebar
  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.
  • Delivery trucks/ increased traffic. Proper traffic control will be provided.

Crafton Center

  • Pour slab on grade GL 4-8
  • Form and grade slab on grade GL 8-13
  • MEP cans & deck inserts
  • Parking Lot C will be CLOSED through the duration of the project.
  • Access to Parking Lot B is from the west stairs only.  Stairs connecting Parking Lot B and C is CLOSED.
  • Temporary pedestrian path of travel around project site marked with signage.
  • Construction noise from on-site activity.
  • Delivery trucks/ increased traffic.  Proper traffic control will be provided.