Week of December 21

Project Activities:

Impact:

PE Complex

  • Closeout documents

 

  • None at this time.

New Science Building

  • Mobilize, layout & pre weld for pre cast panels at the Lab Wing Building
  • Continue to install fire sprinkler hangers, main & branch lines (no vertical drops) on 2nd floor at the Lab Wing Building
  • Continue to install mechanical duct work & in line units on the 1st floor at the Lab Wing Building
  • Layout for overhead utilities and walls penetration on the 1st floor at the Lab Wing Building
  • Fine grade for slab on ground, install crushed rock, vapor barrier & rebar at the Lecture Wing Building
  • Place and finish concrete 2nd level at the Lecture Wing Building

 

  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

OE2 Building

  • East wing exterior framing
  • Installation of rough fire alarm and low voltage conduits on 1st floor
  • Shaft wall installation at elevator
  • 2nd floor MEP rough-in installation
  • Rough carpentry and mechanical wood curbs West & east wing roofing
  • West wing 2nd floor interior framing
  • East wing 2nd floor interior framing
  • Membrane roofing installation
  • Weather barrier installation
  • Removal Of Sidewalk between OE2 and bookstore
  • Correctional work at the HSS Fin supports

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.
  • The temporary fencing around the bookstore will be adjusted in order to complete the sidewalk work.  No access will be allowed on the east side of the bookstore building.
  • Irrigation lines will be cut and capped in order to complete work at the sidewalk.

Crafton Center

  • Sidewalk demo at Classroom Building and west sidewalk
  • Grade at Classroom Building
  • Demo at PL C planters
  • Exterior framing clips on East & South elevations
  • Drywall at exterior parapets
  • Set Air Handler Units on Roof, currently scheduled for 12/22/14
  • Layout & frame exterior walls West, North & East elevations
  • Drywall at parapets
  • Layout and frame 1st floor interior walls
  • Overhead MEP 1st floor
  • MEP rough-in at 1st floor walls
  • Door frames at 1st floor walls
  • Layout and frame 2nd floor interior walls
  • Overhead MEP 2nd floor

 

  • Parking Lot C will be CLOSED through the duration of the project.
  • Access to Parking Lot B is from the west stairs only.  Stairs connecting Parking Lot B and C is CLOSED.
  • Temporary pedestrian path of travel around project site marked with signage.
  • Construction noise from on-site activity.
  • Delivery trucks/ increased traffic.  Proper traffic control will be provided.
  • No Construction Activities 12/25/14 and 12/26/14
  • Sidewalk at Living Wall will be closed.  ADA access as needed.
  • Sidewalk and grassy knoll lawn at Classroom Building will be closed, including access to East side of Classroom Building

M&O

  • Soft and hard demolition
  • Installation of new sanitary sewer line

 

  • Construction noise from on-site activity.
  • Delivery trucks / increased traffic.  Proper control will be provided.
  • Temporary protection will be provided over the excavation of the sanitary sewer line in order to allow for access to the east side of the building.

Week of December 28

Project Activities:

Impact:

PE Complex

  • Closeout documents

 

  • None at this time.

New Science Building

  • Continue to install fire sprinkler hangers, main & branch lines (no vertical drops) on 2nd floor at the Lab Wing Building
  • Continue to install  mechanical duct work & in line units on the 1st floor at the Lab Wing Building
  • Layout for overhead utilities and walls penetration on the 1st floor at the Lab Wing Building
  • Place and finish concrete on the level deck at the Lecture Wing Building
  • Survey for column line offsets for layout 1st and 2nd floor at the Lecture Building
  •  

 

  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

OE2 Building

  • East wing exterior framing
  • Installation of rough fire alarm and low voltage conduits on 1st floor
  • Shaft wall installation at elevator
  • 2nd floor MEP rough-in installation
  • Rough carpentry and mechanical wood curbs West & east wing roofing
  • West wing 2nd floor interior framing
  • East wing 2nd floor interior framing
  • Membrane roofing installation
  • Weather barrier installation
  • Removal Of Sidewalk between OE2 and bookstore
  • Correctional work at the HSS Fin supports

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.
  • The temporary fencing around the bookstore will be adjusted in order to complete the sidewalk work.  No access will be allowed on the east side of the bookstore building.
  • Irrigation lines will be cut and capped in order to complete work at the sidewalk.

Crafton Center

  • Pour sidewalks at Classroom Building, currently scheduled for 12/31/14
  • Form and pour curb and gutter at PL C, currently scheduled for 12/31/14
  • Exterior framing clips on East & South elevations
  • Layout & frame exterior walls North, East & South elevations
  • Drywall at parapets
  • Layout and frame 1st floor interior walls
  • Overhead MEP 1st floor
  • MEP rough-in at 1st floor walls
  • Door frames at 1st floor walls
  • Layout and frame 2nd floor interior walls
  • Overhead MEP 2nd floor

 

  • Parking Lot C will be CLOSED through the duration of the project.
  • Access to Parking Lot B is from the west stairs only.  Stairs connecting Parking Lot B and C is CLOSED.
  • Temporary pedestrian path of travel around project site marked with signage.
  • Construction noise from on-site activity.
  • Delivery trucks/ increased traffic.  Proper traffic control will be provided.
  • No Construction Activities 1/1/15 and 1/2/15
  • Sidewalk at Living Wall will be closed.  ADA access as needed.
  • Sidewalk and grassy knoll lawn at Classroom Building will be closed, including access to East side of Classroom. 

M&O

  • Installation of interior sanitary sewer line
  • Excavation for new warehouse building
  • Installation of conduit for fire alarm relocation

 

  • Construction noise from on-site activity.
  • Delivery trucks / increased traffic.  Proper control will be provided.
  • Shutdown of the fire alarm panel will need to be coordinated on off hours.

Week of January 4

Project Activities:

Impact:

PE Complex

  • Closeout documents

 

  • None at this time.

New Science Building

  • Continue to install fire sprinkler hangers, main & branch lines (no vertical drops) on 2nd floor at the Lab Wing Building
  • Continue to install  mechanical duct work & in line units on the 1st floor at the Lab Wing Building
  • Layout for overhead utilities and walls penetration on the 1st floor at the Lab Wing Building
  • Layout and install top track 1st floor and 2nd floor at the Lecture Wing Building
  • Layout for overhead utilities and wall penetrations at the Lecture Wing Building

 

  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

OE2 Building

  • East wing exterior framing
  • 2nd floor MEP rough-in installation
  • Rough carpentry and mechanical wood curbs West & east wing roofing
  • Installation of CMU veneer
  • Membrane roofing installation
  • Sidewalk between OE2 and bookstore will be poured.

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.
  • The temporary fencing around the bookstore will be adjusted in order to complete the sidewalk work.  No access will be allowed on the east side of the bookstore building.

Crafton Center

  • Exterior framing clips on East & South elevations
  • Layout & frame exterior walls North, East & South elevations
  • Drywall at parapets
  • Roofing membrane
  • Layout and frame 1st floor interior walls
  • Overhead MEP 1st floor
  • MEP rough-in at 1st floor walls
  • Door frames at 1st floor walls
  • Layout and frame 2nd floor interior walls
  • Overhead MEP 2nd floor
  • MEP rough-in at 2nd floor walls

 

  • Parking Lot C will be CLOSED through the duration of the project.
  • Access to Parking Lot B is from the west stairs only.  Stairs connecting Parking Lot B and C is CLOSED.
  • Temporary pedestrian path of travel around project site marked with signage.
  • Construction noise from on-site activity.
  • Delivery trucks/ increased traffic.  Proper traffic control will be provided.
  • Sidewalk at Living Wall will be closed through 1/6/14.  ADA access as needed.
  • Sidewalk and grassy knoll lawn at Classroom Building will be closed through 1/6/14, including access to East side of Classroom. 

M&O

  • Installation of interior sanitary sewer line
  • Excavation for new warehouse building

 

  • Construction noise from on-site activity.
  • Delivery trucks / increased traffic.  Proper control will be provided.