Week of November 16

Project Activities:

Impact:

PE Complex

  • Closeout documents

 

  • None at this time.

New Science Building

  • Place and finish concrete on the south exterior walkaway at the Lab Building Wing (November 13)
  • Place concrete on trenches on the 1st Floor at the Lab Building Wing (November 13)
  • Continue the installation and testing of hydronic piping lines out of the building
  • Continue excavation and installation of plumbing lines on the 1st floor at the Lab Wing Building
  • Continue Install slab on deck rebar at decking on 2nd floor at Lab Wing Building
  • Continue shake out & weld metal decking 2ndfloor and roof level at Lecture Wing Building

 

  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

OE2 Building

  • West wing exterior sheathing
  • West wing 2nd floor interior framing
  • East wing 2nd floor exterior framing
  • East wing 2nd floor interior framing
  • 1st floor rough-in MEP installation
  • 2nd floor rough overhead MEP installation
  • Installation of fire pump station and connection
  • Installation of exterior CMU veneer around 1stfloor electrical room

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.

Crafton Center

  • Grade and form curbs PL C
  • Structural steel welding
  • Misc support steel
  • Lay rebar at 2nd floor deck
  • Pour 2nd floor deck, currently scheduled for11/19/14
  • Roof screen
  • Form and pour roof curbs GL 1-4, currently scheduled for 11/19/14
  • Weld exterior framing clips
  • Layout & frame exterior walls GL North & South elevations
  • Layout and frame interior walls GL 1-6
  • MEP inserts and hangers at deck

 

  • Parking Lot C will be CLOSED through the duration of the project.
  • Access to Parking Lot B is from the west stairs only.  Stairs connecting Parking Lot B and C is CLOSED.
  • Temporary pedestrian path of travel around project site marked with signage.
  • Construction noise from on-site activity.
  • Delivery trucks/ increased traffic.  Proper traffic control will be provided.

Week of November 23

Project Activities:

Impact:

PE Complex

  • Closeout documents

 

  • None at this time.

New Science Building

  • Place and finish concrete on 2nd floor
  • at the Lab Wing Building
  • Place and finish concrete on 1st floor
  • at the Lab Wing Building
  • Install 4” of gravel, vapor barrier & rebar on the 1stand 2nd Floor at the Lab Wing Building
  • Complete installation, welding, flush & hydro test, backfill an compaction of the hydronic piping
  • Shake out & weld metal decking 2nd Floor & Roof Level at the Lecture Building
  • Underground rough installation for Electrical & Plumbing  at the Lecture Building

 

  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

OE2 Building

  • West wing exterior sheathing
  • East wing exterior framing
  • West wing 2nd floor interior framing
  • East wing 2nd floor interior framing
  • 2nd floor rough overhead MEP installation
  • Rough carpentry and mechanical wood curbs West & east wing roofing
  • Installation of exterior CMU veneer around 1stfloor electrical room

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.

Crafton Center

  • Form and pour curbs PL C, currently scheduled for 11/25/14
  • Misc support steel
  • Misc steel welding
  • Form roof curbs GL 5-10
  • Lay rebar at 2nd floor deck
  • Weld exterior framing clips
  • Layout & frame exterior walls North & South elevations
  • Layout and frame interior walls GL 1-6
  • Overhead MEP 1st floor

 

  • Parking Lot C will be CLOSED through the duration of the project.
  • Access to Parking Lot B is from the west stairs only.  Stairs connecting Parking Lot B and C is CLOSED.
  • Temporary pedestrian path of travel around project site marked with signage.
  • Construction noise from on-site activity.
  • Delivery trucks/ increased traffic.  Proper traffic control will be provided.

Week of November 30

Project Activities:

Impact:

PE Complex

  • Closeout documents

 

  • None at this time.

New Science Building

  • Please floor protection at the 2nd floor level at Lab Wing Building
  • Please floor protection at the 1st floor level at Lab Wing Building
  • Layout & install sod cans, deck inserts and sleeves 2nd floor at the Lecture Building
  • Install slab on deck rebar on the 1st and 2nd floor at the Lecture Wing Building
  • Fine grade for slab on grade, forming for install base, vapor barrier & rebar at Lecture Wing Building.
  • Place and finish concrete slab on grade  at the Lecture Building

 

  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

OE2 Building

  • East wing exterior sheathing
  • East wing exterior framing
  • 2nd floor MEP rough-in installation
  • Rough carpentry and mechanical wood curbs West & east wing roofing
  • West wing 2nd floor interior framing
  • East wing 2nd floor interior framing

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.

Crafton Center

  • Misc support steel
  • Misc steel welding
  • Form and pour roof curbs GL 5-10
  • Lay rebar at 2nd floor deck
  • Pour 2nd floor deck
  • Weld exterior framing clips
  • Layout & frame exterior walls North & South elevations
  • Layout and frame interior walls GL 1-6
  • Layout and frame interior walls GL 7-13
  • Overhead MEP 1st floor

 

  • Parking Lot C will be CLOSED through the duration of the project.
  • Access to Parking Lot B is from the west stairs only.  Stairs connecting Parking Lot B and C is CLOSED.
  • Temporary pedestrian path of travel around project site marked with signage.
  • Construction noise from on-site activity.
  • Delivery trucks/ increased traffic.  Proper traffic control will be provided.