Week of July 26

Project Activities:

Impact:

New Science Building (Canyon Halls (CYN)):

  • Prep work to energize VAV’s, phoenix controls
  • Continue to install ceramic tile floors in restrooms at the Lab Wing Building
  • Continue the installation for Firestone Panels east and South at Laboratory Wing Building at Lab Wing Building
  • Metal panels and fume hoods will not be delivered on July 23th, they will be delivered until August 7.
  • Frame bridge soffit between Lab Wing Building and Lecture Building

 

  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

 

OE2 Building (Public Safety & Allied Health Complex (PSAH):

  • Exterior Metal Panel installation
  • Metal fin installation
  • Install fire pump station
  • Interior & Exterior glazing installation
  • Prepare for flatwork at drill yard
  • Landscaping irrigation installation
  • Install paving at fire lane
  • Paver installation at 2nd floor walkways
  • Resilient flooring and carpet installation
  • Ceiling tile installation at 2nd floors
  • Door installation
  • Handrail/Guardrail installation
  • Testing, adjusting and balancing
  • Clearing all items out of parking lot I and striping

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.
  • Delivery trucks/ increased traffic. Proper traffic control will be provided

Crafton Center (CCR):

  • Concrete panel hardware and insulation
  • Metal panels
  • Window Frames and Storefronts
  • Exterior Doors
  • Interior & Exterior Glass
  • Linear Panels at High Ceilings
  • Kitchen Equipment
  • Install MPR Floor Tile
  • 1st Floor Casework
  • Ceiling Tile at 1st floor
  • Ceiling grid at 2nd floor
  • MEP trim at 2nd floor ceilings
  • 2nd Floor Casework
  • Install Rolling Gate @ Service Yard
  • Rolling Doors @ Cart Storage
  • Pour Service Yard Pad
  • Light Pole Bases
  • V Gutter Lot C
  • Finish grade at Ramp

 

  • Access to Parking Lot B is from the west stairs only.  Stairs connecting Parking Lot B and C is CLOSED.
  • Pedestrian path of travel around project site will be marked with signage.
  • Increase in Construction noise from on-site demolition activity.
  • Delivery and Haul-off trucks/ increased traffic.  Proper traffic control will be provided.

PE Complex (Kinesiology, Health Education & Aquatics Center(KHA):

  • Punch Items at Dance Studio.

 

  • Construction noise from on-site activity.

Wayfinding

  • Removal of signage
  • Re- install Handicap signage
  • Removal of signage and bulletin Boards on campus.

 

 

  • Minimal Construction noise due to removal of signage.
  • Impact to parking lot due to the relocation and installation of sign removal, installation and relocation of signs.

Classroom Swing Space

  • Continue installation of Electrical and low voltage for classrooms
  • Finishing Installation of fire alarm system
  • Finishing Misc. work

 

  • None.

 

Week of August 2

Project Activities:

Impact:

New Science Building (Canyon Halls (CYN)):

  • Install Juke ground cover at the south slope
  • Receive, off load & install fume hoods at the Lab Wing Building
  • Install light fixtures, ceiling registers, EMS, FA & speakers
  • Continue the installation of ceramic tile on walls in restrooms at the Lab Wing Building
  • Continue the installation for Firestone Panels east and South at Laboratory Wing Building at Lab Wing Building
  • Install T-Bar grid system at the Lecture Building
  • Frame bridge soffit between Lab Wing Building and Lecture Building

 

  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

 

OE2 Building (Public Safety & Allied Health Complex (PSAH):

  • Exterior Metal Panel installation
  • Metal fin installation
  • Interior & Exterior glazing installation
  • Pour flatwork at drill yard
  • Paver installation at 2nd floor walkways
  • Overhead coiling door installation at apparatus bay
  • Resilient flooring and carpet installation
  • Ceiling tile installation at 2nd floors
  • Handrail/Guardrail installation
  • Testing, adjusting and balancing
  • Clearing all items out of parking lot I and striping

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.
  • Delivery trucks/ increased traffic.

Crafton Center (CCR):

  • Concrete panel hardware and insulation
  • Metal panels
  • Window Frames and Storefronts
  • Exterior Doors
  • Interior & Exterior Glass
  • Linear Panels at High Ceilings
  • Interior Metal & Wood Doors
  • Kitchen Equipment
  • Install MPR Floor Tile
  • 1st Floor Casework
  • Ceiling Tile at 1st floor
  • MEP trim at 2nd floor ceilings
  • Ceiling Tile at 2nd floor
  • 2nd Floor Casework
  • Pour Ramp
  • Demo Paving Parking Lot C
  • Form Curbs Parking Lot C

 

  • Access to Parking Lot B is from the west stairs only.  Stairs connecting Parking Lot B and C is CLOSED.
  • Pedestrian path of travel around project site will be marked with signage.
  • Increase in Construction noise from on-site demolition activity.
  • Delivery and Haul-off trucks/ increased traffic.  Proper traffic control will be provided.

PE Complex (Kinesiology, Health Education & Aquatics Center(KHA):

  • No update

 

  • No update

Wayfinding

  • Install new signs
  • Relocation of signage
  • Stripping of parking lots and curbs
  • Painting of metal frame next to Pool

 

 

  • Minimal Construction noise due to relocation of signage.
  • Parking lot impacts due to the striping of the parking lots and curbs.

Classroom Swing Space

  • Continue installation of Electrical and low voltage for classrooms
  • Finishing Installation of fire alarm system
  • Finishing Misc. work

 

  • None.

 

Week of August 9

Project Activities:

Impact:

New Science Building (Canyon Halls (CYN)):

  • Complete grading & export soil at the south slope at the Lab Wing Building
  • Install light fixtures, ceiling registers, EMS, FA & speakers
  • Install ceramic tile floors & walls in restrooms
  • Continue the installation for Firestone Panels east and South at Laboratory Wing Building at Lab Wing Building
  • Frame bridge soffit between Lab Wing Building and Lecture Building

 

  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

 

OE2 Building (Public Safety & Allied Health Complex (PSAH):

  • Exterior Metal Panel installation
  • Metal fin installation
  • Paver installation at courtyard
  • Landscaping
  • Handrail/Guardrail installation
  • Testing, adjusting and balancing
  • Clearing all items out of parking lot I and striping

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.
  • Delivery trucks/ increased traffic.

Crafton Center (CCR):

  • Concrete panel hardware and insulation
  • Metal panels
  • Interior Glass
  • Linear Panels at High Ceilings
  • Interior Metal & Wood Doors
  • Kitchen Equipment
  • Install MPR Floor Tile
  • Install Concourse Floor Tile
  • 1st Floor Casework
  • Ceiling Tile at 1st floor
  • 2nd Floor Casework
  • Ceiling Tile at 2nd floor
  • Form Curbs at Parking Lot C
  • Pour Curbs at Parking Lot C

 

  • Access to Parking Lot B is from the west stairs only.  Stairs connecting Parking Lot B and C is CLOSED.
  • Pedestrian path of travel around project site will be marked with signage.
  • Increase in Construction noise from on-site demolition activity.
  • Delivery and Haul-off trucks/ increased traffic.  Proper traffic control will be provided.

PE Complex (Kinesiology, Health Education & Aquatics Center(KHA):

  • No update

 

  • No update

Wayfinding

  • Relocated signs
  • Install new signs
  • Stripping of parking lots and curbs

 

 

  • Minimal Construction noise due to relocation of signage.
  • Parking lot impacts due to the striping of the parking lots and curbs.

Classroom Swing Space

  • Continue installation of Electrical and low voltage for classrooms
  • Finishing Installation of fire alarm system
  • Finishing Misc. work

 

  • None.