Week of March 1

Project Activities:

Impact:

PE Complex (Kinesiology, Health Education & Aquatics Center(KHA):

  • Closeout documents
  • None at this time.

New Science Building (Canyon Halls (CYN)):

  • Continue to Install storefront curtain wall system starting on the south elevation at the Lab Wing Building
  • Continue to install hangers & overhead plumbing on 2nd floor at the Lab Wing Building
  • Continue to frame interior and exterior walls, set door frames and install backing at Lab Wing Building and Lecture Wing Building
  • Continue to install overhead RI for electrical & low voltage including hangers, racks & conduit  at the Lecture Wing Building
  • Rough in for electrical & date at Lecture Wing Building
  • In wall rough in plumbing at Lab Wing Building
  • Continue hanging duct work, in line unites, VAV boxes, and OH hydronic piping at Lab Wing building and Lecture Wing building.
  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

OE2 Building (Public Safety & Allied Health Complex (PSAH):

  • East wing exterior plywood installation
  • West wing exterior plywood installation
  • 2nd floor MEP rough-in installation
  • Membrane roofing installation
  • Liquid applied roofing installation
  • CMU veneer installation
  • Storefront frame installation
  • Rough carpentry and mechanical curb installation
  • HSS Fin support rework
  • 2nd floor weather barrier installation
  • 1st floor interior gyp board installation
  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.
  • Delivery trucks/ increased traffic. 

Crafton Center (CCR):

  • Form and pour Service Yard footings
  • Form and pour Service Yard Pad
  • Exterior sheathing East and South elevations
  • Waterproofing at exterior walls
  • Plaster at low roof
  • Sheet metal caps and flashing at high roof
  • Frame interior 1st floor soffits
  • Cement board at 1st floor toilets
  • Drywall at 1st floor
  • Insulation at 1st floor
  • Frame interior walls 2nd floor
  • Overhead MEP 2nd floor
  • Frame interior 2nd floor soffits
  • Cement board at 2nd floor toilets
  • Parking Lot C will be CLOSED through the duration of the project.
  • Access to Parking Lot B is from the west stairs only.  Stairs connecting Parking Lot B and C is CLOSED.
  • Temporary pedestrian path of travel around project site marked with signage.
  • Construction noise from on-site activity.
  • Delivery trucks/ increased traffic.  Proper traffic control will be provided.

M&O

  • Interior framing & complete Dbl wall COR
  • Rough plumbing and electrical work
  • Structural Steel erection
  • Grade around addition
  • Demo of exterior doors and windows
  • Construction noise from on-site activity.
  • Increased traffic due to additional trades. 

Week of March 8

Project Activities:

Impact:

PE Complex (Kinesiology, Health Education & Aquatics Center(KHA):

  • Closeout documents
  • None at this time.

New Science Building (Canyon Halls (CYN)):

  • Continue to install hangers & overhead plumbing on 2nd floor at the Lab Wing Building
  • Continue to frame interior and exterior walls, set door frames and install backing at Lab Wing Building and Lecture Wing Building
  • Continue to install overhead RI for electrical & low voltage including hangers, racks & conduit  at the Lecture Wing Building
  • Rough in for electrical & date at Lecture Wing Building
  • In wall rough in plumbing at Lab Wing Building
  • Continue hanging duct work, in line unites, VAV boxes, and OH hydronic piping at Lab Wing building and Lecture Wing building.
  • Layout excavation for stair at the Lecture Building.
  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

OE2 Building (Public Safety & Allied Health Complex (PSAH):

  • 2nd floor MEP rough-in installation
  • Membrane roofing installation
  • Liquid applied roofing installation
  • CMU veneer installation
  • Storefront frame installation
  • 1st floor interior gyp board installation
  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.
  • Delivery trucks/ increased traffic. 

Crafton Center (CCR):

  • Form and pour Service Yard Pad
  • Exterior sheathing East and South elevations
  • Waterproofing at exterior walls
  • Plaster at low roof
  • Sheet metal caps and flashing at high roof
  • Frame interior 1st floor soffits
  • Cement board at 1st floor toilets
  • Drywall at 1st floor
  • Insulation at 1st floor
  • Frame interior walls 2nd floor
  • Overhead MEP 2nd floor
  • Frame interior 2nd floor soffits
  • Cement board at 2nd floor toilets
  • Drywall at 2nd floor
  • Insulation at 2nd floor
  • Parking Lot C will be CLOSED through the duration of the project.
  • Access to Parking Lot B is from the west stairs only.  Stairs connecting Parking Lot B and C is CLOSED.
  • Temporary pedestrian path of travel around project site marked with signage.
  • Construction noise from on-site activity.
  • Delivery trucks/ increased traffic.  Proper traffic control will be provided.

M&O

  • Interior framing & complete Dbl wall COR
  • Rough plumbing and electrical work
  • Structural Steel erection
  • HVAC rough in
  • Construction noise from on-site activity.
  • Delivery trucks / increased traffic.  Proper control will be provided.

Week of March 8

Project Activities:

Impact:

PE Complex (Kinesiology, Health Education & Aquatics Center(KHA):

  • Closeout documents
  • None at this time.

New Science Building (Canyon Halls (CYN)):

  • Continue to install hangers & overhead plumbing on 2nd floor at the Lab Wing Building
  • Continue to frame interior and exterior walls, set door frames and install backing at Lab Wing Building and Lecture Wing Building
  • Continue to install overhead RI for electrical & low voltage including hangers, racks & conduit  at the Lecture Wing Building
  • Rough in for electrical & date at Lecture Wing Building
  • In wall rough in plumbing at Lab Wing Building
  • Continue hanging duct work, in line unites, VAV boxes, and OH hydronic piping at Lab Wing building and Lecture Wing building.
  • Layout excavation for stair at the Lecture Building.
  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

OE2 Building (Public Safety & Allied Health Complex (PSAH):

  • 2nd floor MEP rough-in installation
  • Membrane roofing installation
  • Liquid applied roofing installation
  • CMU veneer installation
  • Storefront frame installation
  • 1st floor interior gyp board installation
  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.
  • Delivery trucks/ increased traffic. 

Crafton Center (CCR):

  • Exterior sheathing East and South elevations
  • Waterproofing at exterior walls
  • Sheet metal caps and flashing at low and high roof
  • Frame interior 1st floor soffits
  • Cement board at 1st floor toilets
  • Drywall at 1st floor
  • Insulation at 1st floor
  • Frame interior walls 2nd floor
  • Overhead MEP 2nd floor
  • Frame interior 2nd floor soffits
  • Cement board at 2nd floor toilets
  • Drywall at 2nd floor
  • Insulation at 2nd floor
  • Parking Lot C will be CLOSED through the duration of the project.
  • Access to Parking Lot B is from the west stairs only.  Stairs connecting Parking Lot B and C is CLOSED.
  • Temporary pedestrian path of travel around project site marked with signage.
  • Construction noise from on-site activity.
  • Delivery trucks/ increased traffic.  Proper traffic control will be provided.

M&O

  • Interior framing & complete Dbl wall COR
  • Rough plumbing and electrical work
  • Structural Steel erection
  • HVAC rough in
  • Construction noise from on-site activity.
  • Delivery trucks / increased traffic.  Proper control will be provided.