Week of March 22

Project Activities:

Impact:

PE Complex (Kinesiology, Health Education & Aquatics Center(KHA):

  • Destructive testing and inspection of Dance Studio Floor.

 

  • Additional worker in the vicinity of the KHA

New Science Building  (Canyon Halls (CYN)):

  • Exterior/Install Built up roofing system at the Lab Wing Building
  • Exterior/Inspection  of framing & installation of 5/8 at the Lab Wing Building
  • Exterior/ Excavation, sanding install UG SD piping & backfill & compaction at the Lab Wing Building
  • Exterior/Pour Concrete foundation for Stair # 1 (between the buildings)
  • Complete DensGlass on exterior side of parapets at the Lab Wing Building
  • Complete & detail wall framing including the area west of the elevator at the Lab Wing Building
  • Install, test and insulate lab plumbing at the Lab Wing Building
  • Hang mechanical ductwork and related bracing at the Lab Wing Building
  • Install acoustic wall & flute insulation on the 1st floor at the Lab Wing Building
  • Frame out exterior walls including 2nd floor duct shafts at the Lecture Wing Building
  • Install RD/OD piping rough in both floors at the Lecture Wing Building

 

  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

OE2 Building (Public Safety & Allied Health Complex (PSAH):

  • Spray wall formwork & rebar installation
  • 2nd floor MEP rough-in installation
  • Membrane roofing installation
  • Liquid applied roofing installation
  • CMU veneer installation
  • Storefront frame installation
  • 1st floor interior gyp board installation
  • Exterior plywood sheathing installation

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.
  • Delivery trucks/ increased traffic. 

Crafton Center  (CCR):

  • Form and pour West sidewalks
  • Form and pour Service Yard / CMU footings & Pad
  • Complete exterior framing at East and South elevations
  • Exterior sheathing East and South elevations
  • Waterproofing at exterior walls
  • Decking and roofing at exterior soffits
  • Sheet metal caps and flashing at low and high roof
  • Frame interior 1st floor soffits and hard lids
  • Drywall at 1st floor
  • Insulation at 1st floor
  • Tape & Finish 1st floor walls
  • Set electrical and data equipment
  • Frame interior walls 2nd floor
  • Frame interior 2nd floor soffits
  • Prep and paint exposed steel columns

 

  • Parking Lot C will be CLOSED through the duration of the project.
  • Access to Parking Lot B is from the west stairs only.  Stairs connecting Parking Lot B and C is CLOSED.
  • Temporary pedestrian path of travel around project site marked with signage.
  • Construction noise from on-site activity.
  • Delivery trucks/ increased traffic.  Proper traffic control will be provided.
  • East access to Classroom Building will be closed from 3/16/15 – 3/20/15.
  • Pedestrian access to the Living Wall will be closed except for handicap accessibility from 3/16/15 – 3/20/15.
  • Power shut down will be on 3/28/15, and building that will be affected are SSB, SSA, Cafeteria, CDC, and maintenance pad, CL building.

M&O

  • Delivery of Metal Purlins
  • Delivery of Door Frames
  • Installation of Door Frames
  • Installation of Purlins
  • Rough-In electrical
  • Rough-in HVAC
  • Rough-In Plumbing
  • Remove  and move the UPS to M&O bldg. from MSA.

 

  • Construction noise from on-site activity.
  • Delivery trucks / increased traffic.  Proper control will be provided.
  • Parking will be impacted at M&O Bldg. due to large amount of trades working on project. Proper control will be provided.

Week of March 29

Project Activities:

Impact:

PE Complex (Kinesiology, Health Education & Aquatics Center(KHA):

  • Dance studio flooring repairs

 

  • Minimal

New Science Building  (Canyon Halls (CYN)):

  • Exterior/Continue to Install Built up roofing system at the Lab Wing Building
  • Exterior/Excavation, sanding install UG SD piping & backfill & compaction north and east of the Lab Wing Building
  • Exterior/ Install rebar for Stair # 1
  • Install store front curtain wall and door frames on east and west of the Lab Building Wing
  • Install acoustic wall & flute insulation on the 2nd floor at the Lab Wing Building
  • Glazing of the exterior curtain wall store front system at
  • Tape and bed drywall on the 1st Floor at the Lab Wing Building
  • Continue to work on the Sun Shade Fins at Lecture Building
  • Complete OH ductwork, including sealing & testing at VAV’s at the Lecture Wing building

 

  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

OE2 Building (Public Safety & Allied Health Complex (PSAH):

  • Spray wall rebar installation
  • Spray wall concrete pour tentatively scheduled for 3/26/15
  • 2nd floor MEP rough-in installation
  • Membrane roofing installation
  • Liquid applied roofing installation
  • CMU veneer installation
  • Storefront frame installation
  • 1st floor interior gyp board installation

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.
  • Delivery trucks/ increased traffic.  Proper traffic control will be provided.

Crafton Center  (CCR):

  • CMU walls at Cart Storage
  • Connect to Campus permanent power – POWER SHUT DOWN ON 4/5/15 for the SSA, SSB, Café, CL, and CDC.
  • Complete exterior sheathing East and South elevations
  • Waterproofing at exterior walls
  • Window frames and storefronts
  • Decking and roofing at exterior soffits
  • Sheet metal caps and flashing at low and high roof
  • Frame interior 1st floor soffits and hard lids
  • Drywall at 1st floor
  • Insulation at 1st floor
  • Tape & Finish 1st floor walls
  • Cement board at 1st floor toilets
  • Frame interior 2nd floor soffits and hard lids
  • Drywall at 2nd floor
  • Insulation at 2nd floor
  • Prep and paint exposed steel columns

 

  • Parking Lot C will be CLOSED through the duration of the project.
  • Access to Parking Lot B is from the west stairs only.  Stairs connecting Parking Lot B and C is CLOSED.
  • Temporary pedestrian path of travel around project site marked with signage.
  • Construction noise from on-site activity.
  • Delivery trucks/ increased traffic.  Proper traffic control will be provided.
  • Power to buildings CDC, SCC, CL, SSA and SSB will be down on Saturday 3/28/15 between 7am – 10am.

M&O

  • Rough Electrical
  • Electrical inspection
  • Install metal door frames
  • Drywall & Insulation
  • Metal frame and purlins

 

  • Construction noise from on-site activity.
  • Delivery trucks / increased traffic.  Proper control will be provided.
  • Parking will be impacted M&O due to large amount of trades working on project. Proper control will be provided.

week of April 5

Project Activities:

Impact:

PE Complex (Kinesiology, Health Education & Aquatics Center(KHA):

  • Dance studio flooring repairs

 

  • Minimal

New Science Building  (Canyon Halls (CYN)):

  • Continue Tape and bed drywall on the 1st Floor at the Lab Wing Building
  • Hang one side full height drywall at the Lab Wing Building
  • hangers, racks & conduit  at the Lecture Wing Building
  • Continue to work on the Sun Shade Fins at Lecture Building

 

  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

OE2 Building (Public Safety & Allied Health Complex (PSAH):

  • 2nd floor MEP rough-in installation
  • CMU veneer installation
  • Storefront frame installation
  • 1st floor interior gyp board installation

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.
  • Delivery trucks/ increased traffic. 

Crafton Center  (CCR):

  • CMU walls at Cart Storage
  • Waterproofing at exterior walls
  • Window frames and storefronts
  • Sheet metal caps and flashing at low and high roof
  • Drywall at 1st floor
  • Insulation at 1st floor
  • Tape & Finish 1st floor walls
  • Prep & paint 1st floor walls
  • Tile at 1st floor toilets
  • Frame interior 2nd floor soffits and hard lids
  • Drywall at 2nd floor
  • Insulation at 2nd floor
  • Tape & Finish 2nd floor walls
  • Cement board at 2nd floor toilets

 

  • Parking Lot C will be CLOSED through the duration of the project.
  • Access to Parking Lot B is from the west stairs only.  Stairs connecting Parking Lot B and C is CLOSED.
  • Temporary pedestrian path of travel around project site marked with signage.
  • Construction noise from on-site activity.
  • Delivery trucks/ increased traffic.  Proper traffic control will be provided.

M&O

  • Drywall & Insulation
  • Metal Deck installation

 

  • Construction noise from on-site activity.
  • Delivery trucks / increased traffic.  Proper control will be provided.