Week of June 17th
|
| Project Activities: |
Impact: |
|
Electrical Reroute:
- Cable and equipment installation
- Electrical shutdown/connection
- Phone/data shutdown
Projected Completion Date: June 30th, 2013
|
- Pedestrians will be detoured to/from the LRC and the 1st floor of the CHS building. Zoom in on the attached map for pedestrian detours.
- There will be minimal construction noise.
- Sidewalks reopened on June 18th
- Electrical shutdown scheduled for Thursday, June 20th (6pm) –Sunday, June 23rd (will affect PAC, SSA, Cafeteria, SSB, CDC, and LRC)
- Electrical shutdown on Saturday, June 22rd (will affect CHS and LADM Physics and Anatomy labs). Coordination with affected areas is in process.
- Phone/data shutdown scheduled for Saturday, June 22nd (will affect CHS)
|
|
OE2 Demo
- Install construction fencing and signage, walkways, etc.
- Underground site utility investigation
|
- Once construction fencing is installed it will detour pedestrians by alternate route to/from Lot I.
|
|
OE1 Roofing Project
- Mobilization and temporary fencing up around OE1
Projected Completion Date: July 15th, 2013
|
- Due to the shutdown of the building ventilation, OE1 building will be closed for the duration of the project.
|
|
SSB 1st Floor Painting and Flooring Project
- Install flooring (complete 6/17/13)
- CHC Maintenance 6/17 -6/20
- Move-in begins
Projected completion date: June 27, 2013
|
- HWC temporarily located at the Gym
- DSPS temporarily located in the LRC
|