Week of December 14

Project Activities:

Impact:

PE Complex

  • Closeout documents

 

  • None at this time.

New Science Building

  • Continue to install 4” of gravel base, vapor barrier & rebar on the 2nd floor (north side of the Lab Wing Building)
  • Continue to install utility hangers @roof deck for HVAC, electrical and plumbing on 2nd floor at Lab Wing Building
  • Rough in overhead plumbing RD/OD lines on the 2nd floor at the Lab Wing Building
  • Rough in overhead electrical & low voltage on 2nd floor at the Lab Wing Building
  • Layout & install top track on the 1st floor at the Lab Wing Building
  • Layout for overhead utilities and walls penetration on the 1st floor at the Lab Wing Building

 

  • Parking lot “F” and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

OE2 Building

  • West wing exterior sheathing
  • East wing exterior framing
  • 2nd floor MEP rough-in installation
  • Rough carpentry and mechanical wood curbs West & east wing roofing
  • West wing 2nd floor interior framing
  • East wing 2nd floor interior framing
  • Shaft wall installation at the elevators
  • Membrane roofing installation
  • Weather barrier installation

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.

Crafton Center

  • Install Stair #2
  • Exterior framing clips on East & South elevations
  • Roof screen
  • Mechanical/Skylight curbs
  • Layout & frame exterior walls West & North elevations
  • Layout and frame 1st floor interior walls
  • Overhead MEP 1st floor
  • MEP rough-in at 1st floor walls
  • Door frames at 1st floor walls
  • Layout and frame 2nd floor interior walls
  • Overhead MEP 2nd floor

 

  • Parking Lot C will be CLOSED through the duration of the project.
  • Access to Parking Lot B is from the west stairs only.  Stairs connecting Parking Lot B and C is CLOSED.
  • Temporary pedestrian path of travel around project site marked with signage.
  • Construction noise from on-site activity.
  • Delivery trucks/ increased traffic.  Proper traffic control will be provided.

M&O

  • Soft and hard demolition
  • Installation of new sanitary sewer line

 

  • Construction noise from on-site activity.
  • Delivery trucks / increased traffic.  Proper control will be provided.

Week of December 21

Project Activities:

Impact:

PE Complex

  • Closeout documents

 

  • None at this time.

New Science Building

  • Install fire sprinkler hangers, main & branch lines (no vertical drops) on 2nd floor at the Lab Wing Building
  • Install  mechanical duct work & in line units on the 1st floor at the Lab Wing Building
  • Continue to layout for overhead utilities and walls penetration on the 1st floor at the Lab Wing Building
  • Survey for column line offsets for layout 1st and 2nd floor at the Lecture Building
  • Continue to layout and install top track 1st floor and 2nd floor at the Lecture Building
  • Install slab on deck rebar at decking on 2nd floor at the Lecture Building

 

  • Parking lot “F” and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

OE2 Building

  • East wing exterior framing
  • 2nd floor MEP rough-in installation
  • Rough carpentry and mechanical wood curbs West & east wing roofing
  • West wing 2nd floor interior framing
  • East wing 2nd floor interior framing
  • Membrane roofing installation
  • Weather barrier installation

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.

Crafton Center

  • Sidewalk demo at Classroom Building and west sidewalk
  • Grade at Classroom Building
  • Demo at PL C planters
  • Exterior framing clips on East & South elevations
  • Set Air Handler Units on Roof, currently scheduled for 12/22/14
  • Layout & frame exterior walls West, North & East elevations
  • Drywall at parapets
  • Layout and frame 1st floor interior walls
  • Overhead MEP 1st floor
  • MEP rough-in at 1st floor walls
  • Door frames at 1st floor walls
  • Layout and frame 2nd floor interior walls
  • Overhead MEP 2nd floor

 

  • Parking Lot C will be CLOSED through the duration of the project.
  • Access to Parking Lot B is from the west stairs only.  Stairs connecting Parking Lot B and C is CLOSED.
  • Temporary pedestrian path of travel around project site marked with signage.
  • Construction noise from on-site activity.
  • Delivery trucks/ increased traffic.  Proper traffic control will be provided.
  • No Construction Activities 12/25/14 and 12/26/14
  • Sidewalk at Living Wall will be closed.  ADA access as needed.
  • Sidewalk and grassy knoll lawn at Classroom Building will be closed, including access to East side of Classroom. 

M&O

  • Soft and hard demolition
  • Installation of new sanitary sewer line
  • Installation of conduit for fire alarm relocation

 

  • Construction noise from on-site activity.
  • Delivery trucks / increased traffic.  Proper control will be provided.

Week of December 28

Project Activities:

Impact:

PE Complex

  • Closeout documents

 

  • None at this time.

New Science Building

  • Place and finish concrete on the level deck at the Lecture Wing Building
  • Install fire sprinkler hangers, main & branch lines (no vertical drops) on 2nd floor at the Lab Wing Building
  • Install  mechanical duct work & in line units on the 1st floor at the Lab Wing Building
  • Layout for overhead utilities and walls penetration on the 1st floor at the Lab Wing Building
  • Place and finish concrete on the level deck at the Lecture Wing Building
  • Survey for column line offsets for layout 1st and 2nd floor at the Lecture Building
  • Layout and install top track 1st floor and 2nd floor at the Lecture Building

 

  • Parking lot “F” and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

OE2 Building

  • East wing exterior framing
  • 2nd floor MEP rough-in installation
  • Rough carpentry and mechanical wood curbs West & east wing roofing
  • West wing 2nd floor interior framing
  • East wing 2nd floor interior framing
  • Installation of CMU veneer

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.

Crafton Center

  • Pour sidewalks at Classroom Building.
  • Form and pour curb and gutter at PL C
  • Exterior framing clips on East & South elevations
  • Layout & frame exterior walls North, East & South elevations
  • Drywall at parapets
  • Layout and frame 1st floor interior walls
  • Overhead MEP 1st floor
  • MEP rough-in at 1st floor walls
  • Door frames at 1st floor walls
  • Layout and frame 2nd floor interior walls
  • Overhead MEP 2nd floor

 

  • Parking Lot C will be CLOSED through the duration of the project.
  • Access to Parking Lot B is from the west stairs only.  Stairs connecting Parking Lot B and C is CLOSED.
  • Temporary pedestrian path of travel around project site marked with signage.
  • Construction noise from on-site activity.
  • Delivery trucks/ increased traffic.  Proper traffic control will be provided.
  • No Construction Activities 1/1/15 and 1/2/15
  • Sidewalk at Living Wall will be closed.  ADA access as needed.
  • Sidewalk and grassy knoll lawn at Classroom Building will be closed, including access to East side of Classroom. 

M&O

  • Installation of interior sanitary sewer line
  • Excavation for new warehouse building

 

  • Construction noise from on-site activity.
  • Delivery trucks / increased traffic.  Proper control will be provided.