Week of October 26

Project Activities:

Impact:

PE Complex

  • Closeout documents
  • Performing punch list items
  • None at this time.

New Science Building

  • Continue welding of metal decking. 1st floor and 2nd floor at the Lab Wing Building
  • Continue to install slab on deck rebar on
  • 1st floor Lab Wing Building
  • Excavation and installation of plumbing lines on the 1st floor at the Lab Wing Building
  • Continue welding structural steel at
  • Lecture Wing Building
  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE‐1 planter
  • Reopen fall 2015
  • CHS north pedestrian walkway and north‐
  • east staircase are closed.
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on‐site activity

OE2 Building

  • West wing 2nd floor concrete pour currently scheduled for 10‐27‐2014.
  • West wing & east wing roof concrete pour for equipment pads currently scheduled for 10‐29‐2014.
  • West wing exterior framing
  • West wing exterior sheathing
  • West wing 1st floor interior framing
  • West wing 1st floor rough overhead MEP
  • installation
  • West & east wing roofing
  • Drill yard site wall forming & rebar
  • Install fire pump station & connection
  • Temporary non‐accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on‐site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.
  • Delivery trucks/ increased traffic. Proper traffic control will be provided.

Crafton Center

  • Welding of steel connections
  • Pour grade beams GL 6‐13, currently scheduled for 10‐29‐2014
  • Underslab conduits & plumbing GL 6‐13
  • Sand & grade slab on grade GL 6‐13
  • Metal deck welding
  • Weld exterior framing clips
  • Drainage at PL C site walls
  • Backfill PL C site walls
  • Parking Lot C will be CLOSED through the duration of the project.
  • Access to Parking Lot B is from the west stairs only. Stairs connecting Parking Lot B and C is CLOSED.
  • Temporary pedestrian path of travel around project site marked with signage.
  • Construction noise from on‐site activity.
  • Delivery trucks/ increased traffic. Proper traffic control will be provided.

Week of November 2

Project Activities:

Impact:

PE Complex

  • Closeout documents
  • Performing punch list items
  • None at this time.

New Science Building

  • Install slab on deck rebar on 2nd floor
  • Lab Wing Building
  • Continue excavation and installation of plumbing lines on the 1st floor at the Lab Wing Building
  • Excavation, installation and testing ofhydronic piping lines out of the building
  • Place and finish concrete on 1st floor
  • At the Lab Wing Building
  • Seal/cure of the 1st floor concrete at the
  • Lab Wing Building
  • Continue welding structural steel Lecture
  • Wing Building
  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE‐1 planter
  • – reopen fall 2015
  • CHS north pedestrian walkway and north‐
  • east staircase are closed.
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on‐site activity

OE2 Building

  • West wing exterior framing
  • West wing exterior sheathing
  • West wing 1st floor interior framing
  • West wing 1st floor rough overhead MEP
  • installation
  • East wing exterior & interior framing
  • West & east wing roofing
  • Install fire pump station & connection
  • Temporary non‐accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on‐site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.

Crafton Center

  • Welding of steel connections
  • Rebar for slab on grade GL 6‐13
  • Pour slab on grade GL 6‐13, currently scheduled for 11‐6‐2014
  • Metal deck welding
  • Form and pour curbs PL C, currently scheduled for 11‐5‐2014
  • Weld exterior framing clips
  • Layout & frame exterior walls GL 1‐4
  • Irrigation at PL C
  • Parking Lot C will be CLOSED through the duration of the project.
  • Access to Parking Lot B is from the west stairs only. Stairs connecting Parking Lot B and C is CLOSED.
  • Temporary pedestrian path of travel around project site marked with signage.
  • Construction noise from on‐site activity.
  • Delivery trucks/ increased traffic. Proper traffic control will be provided.

Week of November 9

Project Activities:

Impact:

PE Complex

  • Closeout documents
  • Performing punch list items
  • None at this time.

New Science Building

  • Continue the installation and testing ofhydronic piping lines out of the building
  • Place and finish concrete on 2nd floor at the Lab Wing Building
  • Seal/cure of the 2nd floor concrete at the
  • Lab Wing Building
  • Install cans, inserts, sleeves and penetrations on 2nd floor at the Lab WingBuilding
  • Continue welding structural steel Lecture
  • Wing Building
  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE‐1 planter
  • – reopen fall 2015
  • CHS north pedestrian walkway and north‐
  • east staircase are closed.
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on‐site activity

OE2 Building

  • West wing exterior framing
  • West wing exterior sheathing
  • West wing 1st floor rough overhead MEP
  • installation
  • East wing exterior & interior framing
  • West & east wing roofing
  • Temporary non‐accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on‐site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.

Crafton Center

  • Metal deck welding
  • MEP cans & deck inserts
  • Weld exterior framing clips
  • Layout & frame exterior walls GL 1‐4
  • Irrigation at PL C
  • Parking Lot C will be CLOSED through the duration of the project.
  • Access to Parking Lot B is from the west stairs only. Stairs connecting Parking Lot B and C is CLOSED.
  • Temporary pedestrian path of travel around project site marked with signage.
  • Construction noise from on‐site activity.
  • Delivery trucks/ increased traffic. Proper traffic control will be provided.