Week of January 10

Project Activities:

Impact:

New Science Building (Canyon Hall (CYN)):

  • Punch list corrections
  • AV/IT installation
  • Fume Hoods certification
  • Commissioning review

 

  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

OE2 Building (Public Safety & Allied Health Complex (PSAH)):

  • Commissioning
  • Closeout/Punch list Corrections

 

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.
  • Delivery trucks/ increased traffic.

Crafton Center (CCR):

  • Punch list corrections (weekends only)
  • Change order work as authorized
  • Landscape 90 day maintenance period

 

 

  • Minimal construction noise from on-site activity.

 

Wayfinding

  • Punch Walk with AOR
  • Punch list corrections

 

  • None

CHS, OE1, MSA Tenant Improvement Phase 2

  • Installation of White boards at OE1.
  • Installation of shower at M&O Building.
  • Painting wall, doors and trims at CHS.
  • Framing, paint and finish Data cabinet at CHS.
  • Waterproof balcony at CHS.
  • Final clean-up.
  • Punch Walk

 

  • Minimal Impact to parking lot E

CHURN

  • Relocation of Furniture from LADM 1st and 3rd Floor.
  • Faculty Office from SSA to ARTS, and CNTL.
  • Relocation of Physic, Geology and partially CIS

 

  • Minimal Impact to Parking lot E as Corovan Truck will be using couple parking stalls.
  • Path of travel near SSA Building will be will have minimal impacted when relocating the Offices. 

Week of January 17

Project Activities:

Impact:

New Science Building (Canyon Hall (CYN)):

  • Closeout / Punch list corrections
  • AV/IT installation

 

 

  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

OE2 Building (Public Safety & Allied Health Complex (PSAH)):

  • Commissioning
  • Closeout/Punch list Corrections
  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.
  • Delivery trucks/ increased traffic.

Crafton Center (CCR):

  • Punch list corrections (weekends only)
  • Change order work as authorized
  • Landscape 90 day maintenance period

 

  • Minimal construction noise from on-site activity.

 

Wayfinding

  • Punch list corrections

 

 

  • None

CHS, OE1, MSA Tenant Improvement Phase 2

  • Punch list corrections   

 

 

  • None

 

CHURN

  • None

 

  • None 

Classroom Bld. (West Complex)

  • Door Lockdown Hardware Install

 

 

  • None

CDS, Bookstore & CHS

  • Door Lockdown Hardware Install

 

 

  • None

Week of January 24

Project Activities:

Impact:

New Science Building (Canyon Hall (CYN)):

  • Closeout - Punch list corrections

 

  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

OE2 Building (Public Safety & Allied Health Complex (PSAH)):

  • Commissioning
  • Closeout/Punch list Corrections
  • HVAC Training

 

 

  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.
  • Delivery trucks/ increased traffic.

Crafton Center (CCR):

  • Punch list corrections (weekends only)
  • Landscape 90 day maintenance period

 

 

  • None

 

Wayfinding

  • None

 

 

 

  • None

CHS, OE1, MSA Tenant Improvement Phase 2

  • None

 

 

  • None

 

CHURN

  • None

 

  • None 

 

Classroom Bld. (West Complex)

  • Door Lockdown Hardware Install

 

  • None

CDS, Bookstore & CHS

  • Door Lockdown Hardware Install

 

  • None