Week of May 24

Project Activities:

Impact:

New Science Building (Canyon Halls (CYN)):

Exterior

  • Energizing Electrical gears, tentative by June 6th, 2015
  • Framing and inspection of Elevator # 1 by May 26th
  • UG storm drain, fire water, gas at Parking lot. Scheduled to start by May 27th

Interior:

  • Drop in lights on 1st Floor at the Lab Wing Building
  • Continue to install T-bar ceiling grid line, struts and hangers at the Lab Wing Building
  • Continue to install OH power,/Data/Fire alarm at the Lab Wing Building
  • hangers, racks & conduit  at the Lecture Wing Building
  • Continue to work on the Sun Shade Fins at Lecture Building

 

  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

 

OE2 Building (Public Safety & Allied Health Complex (PSAH):

  • CMU Veneer installation
  • Storefront frame installation
  • Exterior Metal Panel installation
  • Exterior soffit sheathing installation
  • Lath and plaster at exterior soffit
  • Weather barrier installation at metal fins
  • Tape and finish 2nd floor interior gyp board
  • Suspended ceiling system installation at 1st and 2nd floor
  • Prime paint installation at 1st and 2nd floors
  • Door and hardware installation at 1st floor

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.
  • Delivery trucks/ increased traffic.

Crafton Center (CCR):

  • Complete waterproofing at East and South Elevations
  • Window frames and storefronts
  • Prep and paint 1st floor walls and ceilings
  • Windows and doors at 1st floor
  • Ceiling grid at 1st floor
  • Floor Tile at Cafeteria/Bookstore
  • Pour Stair 3 threads, currently scheduled for 5/29/15
  • Drywall at 2nd floor
  • Insulation at 2nd floor
  • Tape & Finish 2nd floor walls
  • Tile at 2nd floor toilets
  • Prep and Paint 2nd floor walls
  • Windows and doors at 2nd floor
  • Grade, form, and pour Slab on Grade at Cart Storage, currently scheduled for 5/28/15
  • Form and pour planter/seat walls, currently scheduled for 5/27/15
  • Demo sidewalks South and East sides.

 

  • Parking Lot C will be CLOSED through the duration of the project.
  • Access to Parking Lot B is from the west stairs only.  Stairs connecting Parking Lot B and C is CLOSED.
  • Pedestrian path of travel around project site and at Classroom Building will be marked with signage.
  • Increase in Construction noise from on-site demolition activity.
  • Delivery and Haul-off trucks/ increased traffic.  Proper traffic control will be provided.
  • Access to West ramp at Living Wall will be closed.
  • Access to East wing of Classroom Building will be closed.

M&O      

  • Continue installation of shelving
  • Grade around new warehouse
  • Base & Asphalt
  • AC Start Up
  • Installation of wall fans
  • Programming of lights
  • Install glazing
  • Installation of Insulation

 

  • Construction noise from on-site activity.
  • Increased traffic due to site delivery of material. Proper traffic control will be provided

 

 

Week of June 1

Project Activities:

Impact:

New Science Building (Canyon Halls (CYN)):

Interior:

  • Continue with Drop in lights on 1st Floor and 2nd at the Lab Wing Building
  • Continue to Install T-bar ceiling grid line, struts and hangers at the Lab Wing Building
  • Install aluminum frames and doors
  • Install FP drops and heads in T-Bar ceiling at the Lab Wing Building
  • Continue to install OH power,/Data/Fire alarm at the Lab Wing Building
  • Hang one side full height drywall at the Lab Wing Building
  • Install storefront system at the Lecture Wing Building.  Scheduled by June 28th
  • Continue with hangers, racks & conduit  at the Lecture Wing Building
  • Continue to work on the Sun Shade Fins at Lecture Building

 

  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

 

OE2 Building (Public Safety & Allied Health Complex (PSAH):

  • CMU Veneer installation
  • Storefront frame installation
  • Exterior Metal Panel installation
  • Lath and plaster at exterior soffit
  • Tape and finish 2nd floor interior gyp board
  • Suspended ceiling system installation at 2nd floor
  • Final pain at 1st floor
  • Prime paint installation at 2nd floors

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.
  • Delivery trucks/ increased traffic.

Crafton Center (CCR):

  • Window frames and storefronts
  • Prep and paint 1st floor walls and ceilings
  • Ceiling grid at 1st floor
  • Floor Tile at Cafeteria/Bookstore
  • Drywall at 2nd floor
  • Tape & Finish 2nd floor walls
  • Tile at 2nd floor toilets
  • Prep and Paint 2nd floor walls
  • Windows and doors at 2nd floor
  • Overhead Roll-up doors at Cart Storage and Stockroom
  • Demo sidewalks South and East sides
  • Form sidewalks at South and East sides

 

 

  • Parking Lot C will be CLOSED through the duration of the project.
  • Access to Parking Lot B is from the west stairs only.  Stairs connecting Parking Lot B and C is CLOSED.
  • Pedestrian path of travel around project site and at Classroom Building will be marked with signage.
  • Increase in Construction noise from on-site demolition activity.
  • Delivery and Haul-off trucks/ increased traffic.  Proper traffic control will be provided.
  • Access to West ramp at Living Wall will be closed.
  • Access to East wing of Classroom Building will be closed.

M&O      

  • Installation of Asphalt
  • AC Start Up
  • Installation of wall fans
  • Installation of truncated domes
  • Installation of toilet partitions
  • Test & Balance
  • Seal floors
  • Installation of core cylinders

 

  • Construction noise from on-site activity.
  • Increased traffic due to site delivery of material. Proper traffic control will be provided

 

PE Complex (Kinesiology, Health Education & Aquatics Center(KHA):

  • Remove floor at Dance Studio

 

  • Construction noise from on-site activity.
  • Demolition Haul-off trucks/ increased traffic. 

Week of June 8

Project Activities:

Impact:

New Science Building (Canyon Halls (CYN)):

  • Interior: Install Laboratory casework and equipment at the Lab Wing Building (1st delivery)
  • Continue with Drop in lights on 2nd Floor at the Lab Wing Building
  • Install T-bar ceiling grid line, struts and hangers at the Lab Wing Building
  • Install aluminum frames and doors
  • Install FP drops and heads in T-Bar ceiling at the Lab Wing Building
  • Continue to install OH power,/Data/Fire alarm at the Lab Wing Building
  • Hang one side full height drywall at the Lab Wing Building
  • Install glass at the storefront system at the Lecture Wing Building
  • Start drywall on 1st and 2nd floor at the Lecture Building
  • Continue to work on the Sun Shade Fins at Lecture Building

 

  • Parking lot F and ADA access ramp are temporary closed – reopen fall 2015
  • Extend yellow fence west of OE-1 planter – reopen fall 2015
  • CHS north pedestrian walkway and north-east staircase are closed.  
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

 

OE2 Building (Public Safety & Allied Health Complex (PSAH):

  • CMU Veneer installation
  • Storefront frame installation
  • Exterior Metal Panel installation
  • Lath and plaster at exterior 2nd floor
  • Suspended ceiling system installation at 2nd floor
  • Prime paint installation at 2nd floors

 

  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Temporary fencing is up around project site.
  • Delivery trucks/ increased traffic.

Crafton Center (CCR):

  • Window frames and storefronts
  • Metal panels
  • Concrete panel hardware
  • Ceiling grid at 1st floor
  • MEP trim at 1st floor
  • Floor tile at MP Room and Concourse
  • Kitchen equipment at Cafeteria
  • Casework at 1st floor
  • Tape & Finish 2nd floor walls
  • Prep and Paint 2nd floor walls and ceilings
  • Ceiling grid at 1st floor
  • Form sidewalks at South and East sides
  • Pour sidewalks at South and East sides

 

  • Access to Parking Lot B is from the west stairs only.  Stairs connecting Parking Lot B and C is CLOSED.
  • Pedestrian path of travel around project site and at Classroom Building will be marked with signage.
  • Increase in Construction noise from on-site demolition activity.
  • Delivery and Haul-off trucks/ increased traffic.  Proper traffic control will be provided.
  • Access to West ramp at Living Wall will be closed.
  • Access to East wing of Classroom Building will be closed.

M&O    

  • Walking project to create punch
  • GC Demobilization

 

 

  • Noise due to Demobilization
  • Increased traffic due contractor demobilization & punch work.

PE Complex (Kinesiology, Health Education & Aquatics Center(KHA):

  • Remove floor at Dance Studio

 

  • Construction noise from on-site activity.
  • Demolition Haul-off trucks/ increased traffic.