Week of May 25

Project Activities:

Impact:

CHS & CL Roof

Installation of roofing at CL Building

Roof removal will begin Friday at 3:00p.m.

PE Complex

  • Site walls and ramps
  • Painting
  • Fire Alarm and Electrical work in Aquatics Center (will be coordinated with staff)
  • Gates and fencing in pool are will take place while pool is closed for maintenance

New Science Building

  • Formwork and rebar for columns, walls, and footing  for Lab building
  • Over-excavation Lecture building
  • Haul off dirt from valley to south side. Run 2-3 trucks for 05-27 and 05-28 using Campus Dr. from 6:00am – 2:30pm 
  • Storm drain system installation     
  • Restore the LADM’s north lawn area
  • Parking lot “F” and ADA access ramp are closed
  • Extend yellow fence west of OE-1 planter
  • CHS north pedestrian walkway and north-east staircase are closed.   
  • Delivery trucks/ increased traffic. Proper traffic control will be provided.
  • Construction noise from on-site activity

OE2 Building

  • East wing retaining wall footing excavation
  • East wing retaining wall and footing forming & rebar installation
  • West wing underslab utility installation
  • West wing slab on grade forming and rebar installation
  • Water tie-in within parking lot H
  • Steel delivery to site on 5-27-2014 and 5-28-2014
  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Proceed with caution around back of OE1 and Bookstore buildings. Fencing and recycling dumpster will be adjusted. Ambulances will be moved to parking lot G staff stalls.
  • Parking lot H will be closed all week
  • Parking lot I will have equipment within it for steel delivery Tuesday & Wednesday early morning.
  • Delivery trucks/increased traffic. Proper traffic control will be provided.

Crafton Center

  • Construction Activities:
    • (3) days of Fence erection at Plaza Quad and Lot C
    • Place Red fence screen on day 3
    • Fence erection at Over-flow parking lot
    • Survey
    • Re-route irrigation
    • Safe-off
    • Start demo of site
  • Lot C impact: CLOSED parking lot
  • Temporary pedestrian travel access signs to be posted
  • Construction noise from on-site activity
  • Delivery trucks/ increased traffic. Proper traffic control will be provided.

Week of June 1

Project Activities:

Impact:

PE Complex

  • Finishes
  • Landscape installation
  • Paving at parking lot J
  • Aquatic Center work  will take place while pool is closed for maintenance
  • Portion of parking lot J will be closed for paving.

New Science Building

  • Formwork and rebar for columns, walls and footing for lab building
  • Storm drain system installation
  • Compaction and certify pad for Lecture building
  • Parking lot “F” and ADA access ramp are closed
  • Extend yellow fence west of OE-1 planter
  • CHS north pedestrian walkway and north-east staircase are closed.   
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

OE2 Building

  • East wing retaining wall and footing forming & rebar installation
  • West wing slab on grade forming and rebar installation
  • West wing vapor barrier installation
  • Concrete pour for east wing retaining wall footing and west wing slab on grade. Currently scheduled for 6-05-2014
  • Underground utility installation
  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity
  • Delivery trucks/increase d traffic. Proper traffic control will be provided.

Crafton Center

  • Construction Activities
    • Demolition of site
  • Lot C impact: CLOSED parking lot
  • Temporary pedestrian travel access signs to be posted
  • Construction noise from on-site activity
  • Delivery trucks/ increased traffic. Proper traffic control will be provided

CHS & CL Roof

  • Roof Demo and installation on CL Bldg.
  • Construction noise from on-site activity
  • Hauling of roof tear off & deliveries.

Week of June 8

Project Activities:

Impact:

PE Complex

  • Finishes
  • Landscape installation
  • Delivery trucks/ increased traffic

New Science Building

  • Concrete work at the Lab building footings,  walls and columns
  • Concrete pour #3 for walls for 06-09-2014 (22 trucks)
  • Storm drain system installation
  • Parking lot "F" and ADA access ramp are closed
  • Extend yellow fence west of OE-1 planter
  • CHS north pedestrian walkway and north-east staircase are closed. 
  • Delivery trucks/ increased traffic. Proper traffic control will be provided
  • Construction noise from on-site activity

OE2 Building

  • East wing retaining wall forming & rebar installation
  • West wing steel erection
  • Underground utility installation
  • Temporary non-accessible pedestrian walkway from Lot I to Lot H
  • Bookstore deliveries will be coordinated with M&O
  • Construction noise from on-site activity

New Crafton Center

  • Construction Activities
    • demolition of site
    • Earth moving operations
    • Dust Control
  • Lot C impact: CLOSED parking lot
  • Temporary pedestrian travel access signs are posted
  • Construction noise from on-site activity
  • Delivery trucks/ increased traffic. Proper traffic control will be provided.

CHS & CL Roof

  • Installation of roofing at CL Building
  • Construction noise from on-site activity